All Crossrail articles – Page 9
-
ɫTV
Crossrail hands £1m in compensation payouts to former execs
Resources director Valerie Todd, who left last year, given nearly £445,000
-
ɫTV
Crossrail station integration work to drag on until mid-2020
Scheme's boss Mark Wild made comments at TfL board meeting
-
Comment
Crossrail: The level of denial is incredible
Clearly, Crossrail bosses had trouble with facts staring them in the face
-
ɫTV
‘A quarter of a million tasks to do on Crossrail,’ scheme’s boss reveals
Mark Wild reveals enormity of completion plan
-
ɫTV
Crossrail stations and tunnels ‘to be finished this year’, TfL documents reveal
Papers published ahead of board meeting tomorrow
-
ɫTV
Angry Canary Wharf takes aim at Crossrail, saying boss ‘passing blame’ for railway’s delays
Group rubbishes Mark Wild’s claim it is spending £80m on making station safe and allegations of poor workmanship
-
ɫTV
Crossrail programme ‘a failure’, admits scheme’s boss
Mark Wild also tells MPs he was “surprised by the lack of completion” at the stations when he took top job
-
ɫTV
HS2 looks to bolster board in wake of Crossrail saga
Transport department official has revealed HS2 chair Allan Cook is working to ensure there is the ’right level of challenge’ at board level
-
ɫTV
Bill to bring Canary Wharf station up to scratch will be £80m, Crossrail boss reveals
Mark Wild adds the design of Bond Street won’t be finished until this autumn
-
ɫTV
Former Crossrail boss points finger at supply chain for delays
Andrew Wolstenholme tells MPs project was given timescales that were “materially inaccurate and wrong”
-
ɫTV
Part of Crossrail testing programme slips further behind schedule
Work to run trains close together now won’t start until June, nearly three months after original plan
-
ɫTV
Past and present Crossrail bosses to face MPs, all at the same time
The current and previous project leadership teams will be questioned next week
-
ɫTV
Crossrail told to ‘incentivise’ contractors to get job done
NAO warns contractors unlikely to prioritise Crossrail work on lump-sum, fixed-price contracts
-
Comment
Crossrail: the NAO report shows the dangers of believing your own hype
Blind belief has been this project’s undoing; realism and certainty are now the order of the day
-
ɫTV
Multiplex picked for £50m Crossrail office job at Bond Street
The contractor has been signed up under an early engagement contract
-
Comment
Crossrail: Regrets, it has a few
Today’s NAO report shows a litany of very costly programming mistakes, can the new bosses get it back on track?
-
Features
ɫTV podcast: Crossrail latest, construction's climate change action, and solving the competency problem
Listen on our website here or on iTunes, Spotify, Stitcher or your preferred podcast app
-
ɫTV
Scheme’s boss reveals tunnelling to blame for Bond Street Crossrail delays
Mark Wild told the London Assembly that tunnelling had held up the station by a year
-
ɫTV
Crossrail overspend on stations tops £2bn
National Audit Office report also reveals Crossrail has spent £936m on ‘compensation events’
-
ɫTV
Latest Crossrail delivery timetable to be tested by London Assembly
Crossrail heavy hitters to answer questions on plan to finish late-running rail project