Mark Wild adds the design of Bond Street won鈥檛 be finished until this autumn

crossrail-canary-wharf

The man in charge of Crossrail has said it is having to spend 拢80m to make sure its station at Canary Wharf meets London Underground safety standards with work not expected to finish until the autumn.

Speaking to the Public Accounts Committee yesterday, the project鈥檚 chief executive Mark Wild said: 鈥淲e鈥檝e actually spent nearly 拢80m at Canary Wharf changing the equipment to make it the equivalent safety standards that are required for a London Underground station.

鈥淚t was completed in 2015 but we still haven鈥檛 finished the work at Canary Wharf and we won鈥檛 finish Canary Wharf until September or October this year.

鈥淚t鈥檚 fair to say the quality of the work we鈥檝e found in Canary Wharf, completed by Canary Wharf Group, before my time actually, has had to have a wholesale retrofit, particularly in the safety systems.鈥

The station (pictured), which was built by Canary Wharf Group, cost a total of 拢500m with 拢350m coming from Crossrail and 拢150m from the contractor itself. The design and build deal was agreed in 2008.

But Wild, who became chief executive last November, said Crossrail has been left to foot most of the bill for the remedial work.

He said: 鈥淲e have some commercial conversations with Canary Wharf but, and this is more [former chief executive] Andrew [Wolstenholme鈥檚] gig than mine because it was 2014-15 but I believe we accepted the station [as complete] to some extent, so I think, although there is some commercial conversation with Canary Wharf, my focus is on getting the job done.鈥

Wolstenholme, who was at the same committee hearing, said as the contract had been let as design and build, picking up the snagging bill had been the cheaper option.

He joined Crossrail in 2011 鈥 two years after the Canary Wharf contract was signed.

Wolstenholme said: 鈥淚t was let early because it was private site that had the opportunity to start.

鈥淭he design for the actual railway station, as opposed to the top site, came many years later. This was a risk that the Canary Wharf Group and, I believe, the early part of Crossrail took.

鈥淚t was always likely, as design and build, not to meet the full specification. Canary Wharf Group as a commercial organisation say we are going to build and pay for what was in the original specification.鈥

The news about the ongoing work at Canary Wharf comes after its managing director for strategy Howard Dawber tweeted out a picture of the Crossrail station, designed by Foster + Partners, saying it had been completed 鈥渁head of schedule and on budget鈥.

Meanwhile, Wild also confirmed the extent of the delays on some of the scheme鈥檚 central London鈥檚 stations, saying the design of Bond Street, which is being built by a Costain/Skanska joint venture, will not be finalised for at least another four months.

He said: 鈥淏ond Street is 18 months to two years away from completion. Its design isn鈥檛 complete and its design won鈥檛 be complete until September or October.鈥

Wild said Tottenham Court Road, which is being built by Laing O鈥橰ourke, is the most advanced of the central London stations.

鈥淎lthough it looks physically complete the electrical engineering, the migration of activities, will take us to August or September. Our most advanced station won鈥檛 be finished until August or September.鈥

Wild has previously said Crossrail will not open until March 2021, with Bond Street station opening at an unspecified date afterwards.