Mark Wild told the London Assembly that tunnelling had held up the station by a year

The man responsible for completing Crossrail has revealed that a year-long delay to tunnelling was to blame for the issues that have hit the Bond Street station scheme.

Crossrail

Source: Crossrail

Fronting the London Assembly, Crossrail chief executive Mark Wild said the problems that have arisen on the project, which is being built by a Costain-Skanska joint venture, go all the way back to 2014. 

Last week it was revealed that Bond Street would not open in line with the rest of the central section of Crossrail, meaning it will not be in use until after March 2021.

Wild said: 鈥淭he reasons for the Bond Street delay are quite interesting actually and they are mostly that the tunnelling was a year late at Bond Street, so Bond Street is a year behind every other station because of the tunnelling back in 2014.

鈥淭he top priority at Bond Street is to get the subterranean areas in a position they can support the train rather than everybody waiting to get the train going because Bond Street isn鈥檛 quite ready and that鈥檚 why an intervention is needed at Bond Street.鈥

Wild said while he was not certain when Bond Street would open, he was confident the delay would not extend indefinitely.

He said: 鈥淚t鈥檚 quite uncertain, but it wouldn鈥檛 be many months after the opening of stage three we are just not certain at the moment, but we will become certain.

鈥淚t鈥檚 certainly not the case that Bond Street will go on for years.鈥

Wild was joined at the London Assembly plenary session by Crossrail chair Tony Meggs, TfL commissioner Mike Brown and London mayor Sadiq Khan.