All Crossrail articles – Page 10
-
ɫTV
More grillings coming the way of Crossrail bosses
Public Accounts Committee set to get its chance after last week’s news scheme won’t open until March 2021
-
ɫTV
Office workers getting the shakes from Laing O'Rourke on Crossrail
Contractor says nearby businesses were given warning about the work
-
Comment
Crossrail: Heads would have rolled, if they hadn’t gone already
Who will finally admit it was their fault the job is so late?
-
ɫTV
Crossrail won't open until March 2021
Chief executive says six month opening window to start from October 2020
-
ɫTV
London Assembly says others need to take their share of Crossrail blame, not just Terry Morgan
Former chairman the ‘fall guy’ but ex-chief executives including Andrew Wolstenholme also responsible for debacle
-
ɫTV
New opening date for Crossrail set to be made public next week
TfL chief and London mayor expected to join railway's bosses at London Assembly briefing next Thursday
-
ɫTV
TfL boss facing further grilling over Crossrail woe
London Assembly to question Mike Brown why "nobody seems willing to take responsibility" for scheme's problems
-
ɫTV
Crossrail chief challenged decision to withhold bonus months before scheme bust deadline
City Hall report says Andrew Wolstenholme’s attitude was ‘symptomatic of culture which encouraged denial of responsibility’
-
ɫTV
Crossrail opening ‘could be delayed until 2021’
The “best case scenario” would see Crossrail open in spring 2020
-
ɫTV
More than 6,000 people still working on Crossrail
Councils to be given update on scheme's progress at high-level meeting next month
-
ɫTV
Final bill for Crossrail could rise even further, admits transport minister
Tory peer says last year's £2.8bn bailout might still not be enough
-
ɫTV
New Crossrail completion plan ‘taking longer’ to work out, boss admits
Chief executive Mark Wild says skills shortage is hampering finishing off late-running stations
-
ɫTV
MPs still in the dark over what's gone wrong at Crossrail
Committee orders bosses to explain why scheme will be over a year late and required a £2.8bn bailout
-
ɫTV
'Fundamental issue' with productivity on Crossrail, scheme's boss admits
Mark Wild tells TfL board scheme needs a 'breakthrough'
-
ɫTV
TfL takes £600m hit from Crossrail delay
Transport authority is “assuming” construction costs will not grow beyond the extra funding agreed last December
-
ɫTV
Boss reveals extent of tech work still to complete at Crossrail stations
Mark Wild says host of fit-out jobs including critical communications network not yet finished
-
ɫTV
TfL boss accused of hiding Crossrail problems from London mayor
Crossrail’s chief operation’s director says he was told to keep quiet about difficulties over testing
-
ɫTV
Deputy mayor says ex-Crossrail boss 'misled' London Assembly members
Last March Andrew Wolstenholme gave ‘no indication’ scheme could be late, according to Joanne McCartney
-
Features
Online poll: Will Crossrail EVER open?
This week’s poll: So, it’s definitely not opening this year – but will Crossrail be ready in 2020?
-
ɫTV
China General Nuclear appoints ousted HS2 chair to UK board
Sir Terry Morgan also chaired Crossrail