Skanska has won a 拢90m job to fit-out 866 homes on the first phase of the redevelopment of Battersea Power Station
Carillion, which is the main contractor on the 拢400m first phase of the Battersea development, has awarded the 拢88.6m contract to provide the mechanical and electrical shell, core and fit-out works over two years.
Work on the mechanical and electrical elements is set to commence in September 2014 and scheduled to conclude in October 2016.
Martin Neeson, managing director, said: 鈥淭his contract is great news, not just for Skanska, but also for our client and eventually for those people who will be living in the newly-built homes.
鈥淩esidential schemes are a strategic priority for our engineering business.鈥