Returning a wrecked building to public use is tough enough at the best of times, but when your main contractor goes under, the pressure piles on. Stephen Kennett hears how Chatham Dockyard overcame adversity to open its new cultural hub for the summer tourist season
Nine years ago, Bill Ferris signed an agreement that he hoped would safeguard the future of the Number One Smithery at Chatham Historic Dockyard. He was just in time. As you can see from the photo on this page, the forge in the north Kent dockyards had just about mouldered away. This was a considerable loss to the physical remains of Britain鈥檚 maritime history: for 200 years the smithery had supplied the Royal Navy with everything from mighty anchors to metal deck beams. That work came to a halt in 1972, and 12 years later the dockyard around it was taken out of service. Not long after that, the smithery made its debut on English Heritage鈥檚 buildings at risk register.
The deal that Ferris signed in his capacity as chief executive of the Chatham Historic Dockyard Trust was with the National Maritime Museum and the Imperial War Museum, and it promised to transform the scheduled ancient monument into an archive and visitor attraction.
That promise will be kept this weekend, when the restored smithery is opened to the public. But it very nearly wasn鈥檛. Three months before the project was expected to complete, the main contractor went bust, leaving Ferris and the trust in a sticky situation. Not only had it spent the best part of 10 years planning, raising funds and getting the work under way, but it had an opening date it was determined not to miss.
鈥淛uly 2010 was when we planned to open. The threat of missing that window and losing a whole summer of trade was unthinkable,鈥 says Ferris.
The collapse of mid-sized contractors has become a motif of the recession. In the past month alone, Banner Holdings, the firm behind Rafael Vi帽oly鈥檚 Colchester Arts Centre, has gone into administration, as have Southampton contractor Laishley and Mansfield firm Baggaley and Jenkins.
Less than 12 months earlier, the same fate hit RJ Barwick Construction Services, the 150-year-old Kent contractor that had been awarded the 拢5m contract for the smithery.
When the construction phase of the project began in earnest in July 2008 there were no grounds for pessimism. RJ Barwick was known for its historic building conservation work. Among its restoration projects were Dover castle and Ightham Mote, a National Trust property in Kent. It had also worked on new build schools and social housing.
Nigel Howard, the trust鈥檚 historic environment and building project manager, recalls that, after a lengthy procurement procedure, it was happy with the selection. 鈥淭he contractor fitted with the nature of the project; they were a local firm and when they were on site they had a lot of true craftsmen employed as direct labour,鈥 he says.
What鈥檚 more, a lot of work had already been done to de-risk the project. A full archaeological survey and pile probing had been carried out, which meant any uncertainties with the groundworks - usually the most problematic area of a project - had already been identified. In addition, all the work was being carried out in a weather-tight building.
Construction began on site on 21 July 2008, with completion set for mid-September 2009, after which the specialist fit-out and installation of the collections would begin and end in time for a soft launch in early April. Howard admits it wasn鈥檛 an overly generous programme, but it was doable. 鈥淢ost of the tenders came in at around the 60-week period, so that seemed about right,鈥 he says.
But as work progressed on site the programme began to slip. By August 2009 the project was running a disputed eight to 10 weeks behind programme.
Bob Dollin, a partner in Davis Langdon, says with hindsight there were telltale signs that all was not well. RJ Barwick asked for the quick payment of 拢100,000 to cover the cost of an air-handling unit once it arrived on site. The trust agreed to this. But a few weeks later the full extent of the problems came to light when the M&E subcontractor told the trust and its project managers that they were suspending work as they hadn鈥檛 been paid.
This was particularly frustrating for the trust because it had been paying RJ Barwick before the due date each month. Stephen Prowse, associate director with project manager Appleyards, had to choose between allowing the main contractor go under or working with it and the funders to find a way through the problems.
The trust, Davis Langdon and Appleyards immediately started planning for both eventualities, says Prowse. Security was stepped up around the site to make sure no one turned up out of hours to remove materials and plant. This had to be done subtly. 鈥淢ost of the subcontractors and site staff were, I think, unaware of the severity of the situation and were cracking on at speed,鈥 says Dollin. 鈥淎lso you don鈥檛 want to start rumours flowing that might bring the company down.鈥
Meetings were held with RJ Barwick and the M&E subcontractor to see if a system of direct payment could be set up between the trust and the subcontractor. An arrangement was thrashed out, but it was too late. On 28 August, as Prowse was about to go on holiday, RJ Barwick went into administration.
At this stage the confidential plan, known as Operation Blacksmith, went into full swing. The big question was how to get the procurement process started and the project back on track. The administrator was offering to novate the project to another contractor, but the trust had already decided against this.
鈥淭he problem with novation is that you are waiting for someone else to come in and that could take three weeks to sort out,鈥 says Dollin. 鈥淎nd there鈥檚 no guarantee it will be three weeks or that they will come up with a company you think is appropriate.鈥
If the trust had any chance of meeting the July opening date it knew it had to take control. Within half an hour of receiving the administration notice, the site agent was handed a letter saying the trust was taking charge of the site.
This left the trust with two options. It could re-employ the incumbent subcontractors and manage the project itself or employ a completion contractor. It opted for the latter. 鈥淲e decided the project wasn鈥檛 complete enough,鈥 says Prowse. Dollin says he thought the process of appointing a new contractor might take six weeks; in fact it took 12. In hindsight, he says, even this was pretty good.
The first step in the process was to evaluate the exact state of progress of the build and what materials were on site and who owned them. This turned out to be a minefield. Materials that have already been fixed count as work executed and are owned by the client, but materials stored on site are more contentious. Resolving that problem involved delving into the contracts between RJ Barwick and the subcontractors.
As a result of the downturn there were plenty of contractors interested in taking on the job, but projects of this nature can be high risk and the trust made it clear that completion wasn鈥檛 to be at any cost.
After a competitive two-stage tender process, ISG signed a 拢2.1m contract to complete the job. This is between 拢700,000 and 拢1m above the original cost of the building work, which will be met in part by the performance bond procured on the contract with RJ Barwick. ISG says its strategy was comprehensive. It drew up an extensive schedule of information to evaluate the state of the project and worked out a detailed programme for completion. 鈥淭his was so we could come to the table and flush out all the issues and then look at the minimum time required on site to get the job done,鈥 says Stuart Deverill, director of the refurbishments division of ISG.
By now all the programme鈥檚 float had been used up. To add to the pressure, specialist displays and archives were already being manufactured, so a fast-track, 27-week programme had to be developed. And it was no longer possible to segregate the construction and specialist fit-out works as planned. The exhibition spaces were a priority, says Prowse, as these would be open to the public. Work was also speeded up on the restricted areas where the archives were to be stored, to leave time for the humidity to stabilise and the artefacts to be brought in.
鈥淲hen you get an issue like a contractor failing on you it has a bit of an effect on motivation,鈥 says Deverill. 鈥淲e had to come in and be positive and forceful.鈥 Only half of the incumbent subcontractors were re-employed on the project. 鈥淭hat鈥檚 because we were looking for buy-in and who would work as a team and had the get up and go needed.鈥
The Number One Smithery is to open this weekend, just in time for the summer rush of visitors. Ferris says there was never a point when he didn鈥檛 think they would deliver the project, although he concedes: 鈥淚t鈥檚 later than I would have liked, which peeves me.鈥
But given the problems the team has faced, the fact that it鈥檚 opening at all for the summer crowds must come as a relief.
Turning a crumbling monument into a modern museum
The smithery building once housed huge steam hammers and forges that produced everything from anchors to metal ribs and deck beams for vessels assembled at the dockyard. Built in 1808, the brick structure changed and grew through the 19th and 20th centuries to meet the increasing demand for iron in shipbuilding, right up until 1972 when it became redundant. From then on the building fell into decline. Exposure caused by the derelict roof and unstable sub-soil led to extensive damage to the brickwork and superstructure and this led to the building being placed on English Heritage鈥檚 at risk register.
Part of the problem with restoring the building was that no use could be found for it, says Bill Ferris, chief executive of Chatham Historic Dockyard Trust. As one of 47 scheduled ancient monuments on the site, the smithery has repeatedly been sidelined. The answer came in 2001 when an agreement was reached to use it to rehouse collections from the National Maritime Museum and Imperial War Museum.
The tricky bit was how to transform a scheduled ancient monument and grade II*-listed building in a bad state of repair into secure, environmentally controlled spaces, without compromising the historic fabric.
The challenge fell to architect van Heyningen and Haward. Partner Josh McCosh says the idea was to create buildings within a building for the series of high-tech display galleries, exhibition spaces, education areas and storage vaults.
鈥淭he most difficult thing was that you have a fantastic building that is utterly unsuitable for putting ship models in,鈥 says McCosh. 鈥淭he architectural strategy of creating buildings within this building is the key to unlocking its potential. Without it you would be forced to upgrade the historic fabric of the building in a way that would be incredibly destructive, to the extent that it wouldn鈥檛 get permission.鈥
As it is, the steel frame and blockwork structures sit on their own piled foundations and have minimal impact on the original building fabric, allowing its industrial heritage to be left on display. For the archives, extra-thick walls, high-levels of insulation and low-level heating help maintain the carefully regulated environmental conditions required.
The first phase of the project was to carry out emergency stabilisation, which involved underpinning some of the external walls and reroofing the entire building to make it watertight.
An extensive industrial archaeological survey followed. This exposed much of the original floor and positions of the workstations. It also included pile probing, which helped de-risk the main construction package. The location of concrete and stone bases where the original machinery would have sat were identified, which could have caused problems when the piles to support the new buildings were installed.
Construction of the new structures and conservation and repair of the existing structure could then begin in earnest. The original plan had been to complete this stage of the works before the fit and installation of the collection began, but because the main contractor went into administration the programme was condensed (see main story).
Danger signs
Your main contractor may be in trouble if it:
- l Requests payment for large-cost items before they arrive on site
- l Calls for additional information to slow progress
- l Asks for early payments
- l Major subcontractors notify you that they have not been paid on time
Lessons learned
- l Encourage subcontractors to come forward early if there are payment problems
- l Ensure there is a performance bond in place
- l Always have a plan B
- l Obtain subcontractor warranties as soon as possible after they complete their work
- l Increase site security during the standstill period to protect goods and materials
Project team
Client Chatham Historic Dockyard Trust
Architect van Heyningen and Haward
Conservation architect Purcell Miller Tritton
Project manager Appleyards
Quantity surveyor Davis Langdon
Structural engineer Price & Myers
M&E engineers Max Fordham
Museum design Land
Original main contractor RJ Barwick
Completion contractor ISG
No comments yet