Tony Blackler

  • Tony Blackler
    Comment

    Final certificates: It’s not over yet

    2015-03-26T06:00:00

    Challenges to a final certificate through the courts or by arbitration are straightforward but if a contractor challenges via adjudication then procedural mishaps can occur

  • Tony Blackler
    Comment

    Collateral damage: Liability under collateral warranties

    2010-07-23T00:00:00

    Leaseholders or buyers of buildings should be able to pre-empt arguments from contractors to escape liability under collateral warranties

  • Tony Blackler
    Comment

    Concurrent delays: Doing the splits

    2008-06-06T00:00:00

    The City Inn case throws up a logical approach to granting extensions of time due to concurrent delays – if the delay has two causes, then why not apportion responsibility accordingly?

  • Comment

    Fill in this brief questionnaire

    2007-08-10T00:00:00

    What does ‘dispute’ mean? When are two disputes linked? When are they not linked? If an adjudicator decides unlinked disputes, is his decision invalid? For one or both? How much sense does all this make …?

  • Comment

    The common touch

    2001-10-19T00:00:00

    We know that pay-when-paid clauses were partially outlawed by the Construction Act, but how do they fare under common law?

  • Comment

    The fireproof contractor

    2001-09-07T00:00:00

    At last someone is looking into the insurance provisions of JCT80. At the moment, the issue of liability is nothing short of bewildering

  • Comment

    Cut us some slack

    2001-07-13T00:00:00

    Adjudication is increasingly dealing with matters that are difficult to sort out within 28 days. It would be fairer to give adjudicators the right to extend the time limit.

  • Comment

    Blame the parents

    2001-06-01T00:00:00

    An effective way to get results in a dispute with A subsidiary is to launch an action against its parent company on the basis of a parent company guarantee

  • Features

    Breaking up is hard

    2001-03-23T00:00:00

    Tony Blackler - Common law may come into play when parties to a contract fall out – although its application in construction disputes is far from clear-cut.

  • Comment

    Getting off the hook

    2001-01-26T00:00:00

    If a designer makes a mistake, when does the obligation to correct it expire? After the relevant bit is built? After practical completion? After the final certificate? Or never …

  • Features

    Is that your final answer?

    2000-11-24T00:00:00

    The JCT must clarify how far the final certificate puts an end to liability, particularly now that a new ruling further complicates the issue by stating that contractors can later be sued only for faults relating to design

  • Features

    Where do you draw the line?

    2000-04-20T00:00:00

    The Plant Construction vs Clive Adams and Another case was the first time that the courts have ruled on a contractor’s obligation to warn of potential hazards in design and construction plans.

  • Features

    Relationship difficulties

    1999-07-09T00:00:00

    There is a consensus that partnering is the way forward. But the concept is vague, and it may have unexpected effects on relationships within the project team – it may even provide contractors with brand-new excuses.

  • Features

    Plane tale of third parties

    1999-05-14T00:00:00

    Much of the debate on the proposed Contracts Bill centres on the implications of a clause that confers potentially troublesome benefits on third parties not privy to a contract. A flight of fancy or a real worry?