Costing Steelwork is a series from Aecom, BCSA and Steel for Life that provides guidance on costing structural steelwork. This quarter provides a market update and updates the five cost models previously featured in Costing Steelwork

Costing Steelwork cover 23 image

Construction new work output rose by almost 4% over the 12 months to Q3 2022 in the latest construction output data release from the Office for National Statistics. Using the monthly data points, the yearly change at November was slightly lower at 3% than the headline measure. Housing output remained the primary driver of industry growth. A solid contribution came from the private commercial sector in the third quarter, with a 7.4% increase over the year at Q3 and a strong quarter-on-quarter improvement. An area of concern was a drop in volume in the repair and maintenance sector between Q2 and Q3. This is the largest construction sub-sector, so is influential to headline measures of recorded construction output.

Construction sector sentiment maintained its broadly neutral level across the fourth quarter, as most sub-sectors saw continuing good workload levels. This momentum is likely to hold, in spite of the notable operational issues in play. Overall construction output settled into a steady rate of growth over 2022, hitting something of a sweet spot in consistency after the topsy-turvy preceding two years. With economic clouds gathering elsewhere, the construction sector still offers consistency of workload going into this year.

Business sentiment surveys almost all report subdued or gloomier assessments of the domestic trading environment. Many have extended trends that started back in the second quarter of 2022. In spite of the neutral GDP report in December, the collection of business sentiment surveys are mostly in line with each other 鈥 confirming emerging trends, the challenges facing businesses, and an outlook that is less certain. The likelihood of a low-growth environment across 2023 is therefore high.

Specific business issues mentioned often in the surveys all reference now perennial issues, many of which pre-date the invasion of Ukraine and its spill over into higher energy costs. This issue alone would be the cause for significant business problems. Instead, there are a range of significant disruptive and challenging issues that firms are grappling with at present. There are also structural industry issues around labour supply. The impact of these challenges and the pressures they are creating are evident on financial statements and will continue into the medium term.

Costs of borrowing and finance will be one of the major issues facing all businesses in 2023. Tighter financing conditions extend into the operational aspects of businesses. Short-term lending will inevitably be more costly, as will longer-term funding mechanisms too. The tighter cost of borrowing environment has implications for the construction sector 鈥 either directly or indirectly 鈥 with downside risks increasing for related construction activity. Higher funding costs for construction projects do not usually help to support the viability equation, especially as costs of borrowing have been historically low over an extended period of time.

By way of better news, construction input cost inflation continued to slow over the fourth quarter. Aecom鈥檚 building cost index 鈥 a composite measure of materials and labour costs 鈥 increased by 8.5% over the 12 months to Q4 2022. This is a notably reduced rate of inflation from the mid-year peak when it was nearer to 14%. The lower rate of inflation will help the supply chain eventually; however, immediate relief for projects will be minimal and depend on where each project is in its build programme. Newer projects are likely to feel greater benefit from this lower rate of input cost inflation, especially since there is likely to be a narrower difference currently between input costs and recent tender prices. At 8.5%, though, input cost inflation is still well above any long-run average.

Metals and timber-based work items were the index items recording the lowest or negative rates of inflation. This reflects the deflationary trends seen for metals and timber commodities for much of the last six months, now coming through into related construction products and trades. A range of chunky materials price list increases are scheduled for early 2023, which is a sign that despite the headline, aggregate rate of input cost inflation slowing, there are still pockets of exceptionally high cost pressure working their way through the supply chain. Sterling rose slightly in Q4, which should act to temper some of the imported inflationary trends. However, the rise was more related to marginal US dollar depreciation on the prospects for less aggressive changes to US monetary policy rather than to an improving outlook for the UK economy.

It is generally believed that the UK is in the early stages of an economic downturn, in spite of ONS data yet to confirm this. It seems unlikely that organisations such as the Bank of England would expressly state this gloomy prognosis without their own supporting data to justify this position. The Bank has often highlighted the 鈥渘arrow path鈥 it is treading between raising interest rates to engineer a fall in the rate of inflation, and consequent impacts to the economy from higher interest rates. Combined with the relentless inflationary trends already affecting most areas of the country, rising costs of borrowing and lending are certain to further impact business and household spending.

It will take some time for any downturn to evolve, and in the meantime the construction industry鈥檚 current momentum will provide some insulation and cover to a slowdown taking hold in other economic sectors. However, we are currently experiencing a softening of steel prices with the base costs in Q1 2023 slightly lower than in Q4 2022. Overall 2023 is still likely to be a tale of two halves, each with contrasting narratives and underlying currents. The ongoing mix of perennial issues and current workload momentum will propel tender price inflation over the first half of 2023, with expected adjustments over the second half of the year. Aecom鈥檚 baseline forecast for tender prices is a 5% increase from Q4 2022 to Q4 2023, and a 3.5% increase from Q4 2023 to Q4 2024. The balance of risks to forecasts of price trends remain to the upside over the near term.

Figure 1: Tender price inflation, Aecom Tender Price Index, 2015=100

     Forecast*

Quarter

2018

2019

2020

2021

2022

2023

2024

1

113.2

117.9

120.4

120.0

131.2

143.0

149.8

2

113.6

118.3

121.0

122.6

134.5

144.6

151.0

3

115.4

119.3

119.1

125.3

138.1

146.2

152.2

4

117.3

119.8

119.1

127.5

141.8

148.3

153.4

Sourcing cost information

Cost information is generally derived from a variety of sources, including similar projects, market testing and benchmarking. Due to the mix of source information it is important to establish relevance, which is paramount when comparing buildings in size, form and complexity.

Figure 2 represents the costs associated with the structural framing of a building, with a BCIS location factor of 100 expressed as a cost/m虏 on GIFA. The range of costs represents variances in the key cost drivers. If a building鈥檚 frame cost sits outside these ranges, this should act as a prompt to interrogate the design and determine the contributing factors.

The location of a project is a key factor in price determination, and indices are available to enable the adjustment of cost data across different regions. The variances in these indices, such as the BCIS location factors (figure 3), highlight the existence of different market conditions in different regions.

To use the tables:

1. Identify which frame type most closely relates to the project under consideration

2. Select and add the floor type under consideration

3. Add fire protection as required.

For example, for a typical low-rise frame with a composite metal deck floor and 60 minutes鈥 fire resistance, the overall frame rate (based on the average of each range) would be:

拢165.00 + 拢110.00 + 拢26.00 = 拢301.00

The rates should then be adjusted (if necessary) using the BCIS location factors appropriate to the location of the project.

Figure 2: Indicative cost ranges based on gross internal floor area

TYPEBase index 100 (拢/m2)Notes

Frames

   

Steel frame to low-rise building 

149-181

Steelwork design based on 55kg/m2

Steel frame to high-rise building 

251-284

Steelwork design based on 90kg/m2

Complex steel frame

284-335

Steelwork design based on 110kg/m2

Floors

   

Composite floors, metal decking and lightweight concrete topping

86-134

Two-way spanning deck, typical 3m span with concrete topping up to 150mm

Precast concrete composite floor with concrete topping

125-176

Hollowcore precast concrete planks with structural concrete topping spanning between primary steel beams

Fire protection

   

Fire protection to steel columns and beams (60 minutes resistance)

22-31

Factory applied intumescent coating

Fire protection to steel columns and beams (90 minutes resistance)

26-42

Factory applied intumescent coating

Portal frames

   

Large-span single-storey building with low eaves (6-8m)

109-143

Steelwork design based on 35kg/m2

Large-span single-storey building with high eaves (10-13m)

132-170

Steelwork design based on 45kg/m2

Figure 3: BCIS location factors, as at Q1 2023

LocationBCIS IndexLocationBCIS Index

Central London

127

Nottingham

103

Manchester

103

Glasgow

92

Birmingham

97

Newcastle

91

Liverpool

98

Cardiff

94

Leeds

92

Dublin

100*

*Aecom index

 

Steel For Life sponsors

Sponsorship Table 2023 v2

Cost comparison updates

This quarter鈥檚 Costing Steelwork provides an update of the five previously featured cost comparisons covering: offices, education, industrial, retail and mixed-use

These five projects were originally part of the Target Zero study conducted by a consortium of organisations including Tata Steel, Aecom, SCI, Cyril Sweett and the BCSA in 2010 to provide guidance on the design and construction of sustainable, low- and zero-carbon buildings in the UK. The cost models for these five projects have been reviewed and updated as part of the Costing Steelwork series. The latest cost models as of Q1 2023 are presented here. 

Warehouse-1 CMYK copy 2

Distribution warehouse, ProLogis Park, Stoke-on-Trent

Costing steelwork: offices update

Below is an update to the offices cost comparison originally published in the Costing Steelwork Offices feature in 好色先生TV magazine in April 2017.

One Kingdom Street, London, key features

  • 10 storeys, with two levels of basement
  • Typical clear spans of 12m x 10.5m 
  • Three cores 鈥 one main core with open atrium, scenic atrium bridges and lifts
  • Plant at roof level

Cost comparison

Two structural options for the office building were assessed (as shown in figure 4): 

  • Base case 鈥 a steel frame, comprising fabricated cellular steel beams supporting a lightweight concrete slab on a profiled steel deck
  • Option 1 鈥 350mm-thick post-tensioned concrete flat slab with a 650mm x 1,050mm perimeter beam.

The full building cost plans for each structural option have been reviewed and updated to provide current costs at Q1 2023. Over the course of the year increased costs have been largely offset by contractors working on reduced or no margin. The costs, which include preliminaries, overheads, profit and a contingency, are summarised in figure 4.

The cost of the steel composite solution is 5% higher than for the post-tensioned concrete flat slab alternative for the frame and upper floors, but 2% lower on a total building basis. The lighter frame and faster erection result in reduced foundations and a shorter programme. The latter is the main reason for the lower cost.

Figure 4: Key costs 拢/m虏 (GIFA), for City of London office building

Elements Steel compositePost-tensioned concrete flat slab 

Substructure

90

95

Frame and upper floors

553

542

Total building

3,480

3,563

Costing steelwork: education update

Below is an update to the education cost comparison originally published in the Costing Steelwork Education feature in 好色先生TV magazine in July 2017.

Christ the King Centre for Learning, Merseyside, key features

  • Three storeys, with no basement levels
  • Typical clear spans of 9m x 9m
  • 591m2 sports hall (with glulam frame), 770m2 activity area and atrium
  • Plant at roof level 

Cost comparison

Three structural options for the building were assessed (as shown in figure 5), which include:

  • Base case 鈥 steel frame, 250mm hollowcore precast concrete planks with 75mm structural screed
  • Option 1 鈥 in situ 350mm reinforced concrete flat slab with 400mm x 400mm columns
  • Option 2 鈥 steel frame, 130mm concrete topping on structural metal deck.

The full building cost plans for each option have been updated to provide current costs at Q1 2023. The comparative costs highlight the importance of considering total building cost when selecting the structural frame material.

The concrete flat slab option has a lower frame and floor cost compared with the steel composite option, but on a total-building basis, the steel composite option has a lower overall cost of 拢3,825/m虏 against 拢3,861/m虏. This is because of lower substructure and roof costs, alongside lower preliminaries resulting from the shorter programme.

Figure 5: Key costs 拢/m虏 (GIFA), for Merseyside secondary school

Elements Steel + precast hollow-core planksIn situ concrete flat slabSteel composite

Frame and upper floors

369

322

337

Total building

3,892

3,861

3,825

Costing steelwork: industrial update

Below is an update to the industrial cost comparison originally published in the Costing Steelwork Industrial feature in 好色先生TV magazine in October 2017.

Distribution warehouse in ProLogis Park, Stoke-on-Trent, key features

  • Warehouse: four-span, steel portal frame, with a net internal floor area of 34,000m2
  • Office: 1,400m2, two-storey office wing with a braced steel frame with columns

Cost comparison

Three frame options were considered:

  • Base option 鈥 a steel portal frame with a simple roof solution
  • Option 1 鈥 a hybrid option: precast concrete column and glulam beams with timber rafters
  • Option 2 鈥 a steel portal frame with a northlight roof solution.

The full building cost plans for each option have been updated to provide costs at Q1 2023. The steel portal frame provides optimum build value at 拢879/m虏; glulam is least cost-efficient. This is primarily due to the cost premium for the structural members necessary to provide the required spans, which are otherwise efficiently catered for in the steelwork solution.

With a hybrid, the elements are from different suppliers, which raises the cost. The northlights option is directly comparable with the portal frame in relation to the warehouse and office frame. The variance is in the roof framing as the northlights need more of this. Other additional costs relate to the glazing of the northlights.

Figure 6: Key costs 拢/m2 (GIFA), for Stoke-on-Trent distribution warehouse

Elements Steel portal frameGlulam beams + purlins + concrete columnsSteel portal frame + north-lights

Warehouse

122

178

141

Office

180

216

180

Total frame

125

180

143

Total building

879

945

921

Costing steelwork: retail update

Below is an update to the retail cost comparison originally published in the Costing Steelwork retail feature in 好色先生TV magazine in January 2018.

Asda food store, Stockton-on-Tees,

key features

  • Total floor area of 9,393m2
  • Retail area based on 12m x 12m structural grid

Cost comparison

Three frame options were considered (as shown in figure 7) to establish the optimum solution for the building, as follows:

  • Base option 鈥 a steel portal frame on CFA piles
  • Option 1 鈥 glulam timber rafters and columns on CFA piles
  • Option 2 鈥 a steel portal frame with a northlight roof solution on driven steel piles.

The full building cost plans for each option have been updated to provide costs at Q1 2023. The steel portal frame provides the optimum build value at 拢3,185/m虏, with the glulam option the least cost-efficient. The greater cost is due to the direct comparison of the steel frame solution against the glulam columns and beams/rafters. A significant proportion of the building cost is in the M&E services and fit-out elements, which reduce the impact of the structural changes.

The northlights option is directly comparable with the portal frame in relation to the main supermarket 鈥 the variance is in the roof framing as the northlights require more. Additional costs beyond the frame are related to the glazing of the northlights and the overall increase in relative roof area.

Figure 7: Key costs 拢/m2 (GIFA), for Stockton-on-Tees food store

Elements Steel portal frameGlulam timber rafters + columnsSteel portal frame + north-lights

Structural unit cost

183

221

207

Total building unit cost

3,185

3,230

3,198

Costing steelwork: mixed-use update

Below is an update to the mixed-use cost comparison originally published in the Costing Steelwork mixed-use focus feature in 好色先生TV magazine in April 2018.

Holiday Inn tower, MediaCityUK, Manchester

  • 17-storey tower 
  • 7,153m2 of open-plan office space on five floors (floors two to six)
  • 9,265m2 of hotel space on eight floors (floors eight to 15)

The gross internal floor area of the building is 18,625m2. The 67m-high building is rectilinear with approximate dimensions of 74m x 15.3m. 

Cost comparison

Three frame options were considered to establish the optimum solution for the building:

  • Base option 鈥 steel frame with Slimdek floors
  • Option 1 鈥 concrete flat slab
  • Option 2 鈥 composite deck on cellular beams (offices) and UCs used as beams (hotel).

The full building cost plans for each option have been updated to provide costs at Q1 2023. The steel frame with composite deck continues to provide the optimum build value, with the overall building cost at 拢3,277/m2.

Options 1 and 2 are arguably more typical for this building type. The base case structure is an unusual solution due to a decision to change the residential accommodation to office floors at a very late stage 鈥 time constraints precluded redesign of the tower block, hence the original Slimdek design was constructed.

Figure 8: Key costs 拢/m2 (GIFA), for hotel/office building in Manchester

ElementsSteel frame with  SlimdekConcrete flat slabComposite deck on cellular beams (offices) and UCs used as beams (hotel)

Structural unit cost

681

517

465

Total building unit cost

3,546

3,358

3,277

This Costing Steelwork article produced by Patrick McNamara (director) and Michael Hubbard (associate) of Aecom is available at .

The data and rates contained in this article have been produced for comparative purposes only and should not be used or relied upon for any other purpose without further discussion with Aecom. Aecom does not owe a duty of care to the reader or accept responsibility for any reliance on the article contents