Use of groundwater from gravel beds could help cut energy and carbon emissions by half

The Tate Modern will next week begin work on a plan to use groundwater for heating and cooling its 拢215m Herzog & de Meuron-designed extension.

On Monday, consulting engineer Max Fordham Partnership will begin drilling 10m boreholes into the gravel which lies deep beneath the site, on the Thames鈥 former flood plain. The project is thought to be the first of any scale to take water from Thames gravel beds.

Previous schemes in London, including the Royal Festival Hall refurbishment, which Max Fordham also designed, have made use of the water contained in a chalk aquifer, 100-120m below ground level. However, this option is now highly regulated by the Environment Agency because of concerns that aquifers which supply drinking water could be contaminated.

The use of the gravel water at Tate Modern is part of a strategy to cut 54% of energy and 44% of carbon dioxide emissions from the building, which is scheduled to open in 2012.

Mark Nutley, Max Fordham鈥檚 project manager, said the system would use the differential between the air temperature and the 14-15脼C underground water to heat and cool the space. This 鈥渙pen loop鈥 system uses a heat pump to extract energy from the groundwater to heat the building in the winter and cool it in the summer. The water is then fed back into the gravel bed.

US engineer Parsons Brinckerhoff is providing technical expertise on the borehole procedure.

The project is thought to be the first of any scale to take water from Thames gravel

The extension will still draw 70% of its heat from the neighbouring EDF substation, which is being moved to accommodate it.

The scheme received planning consent on 1 April.


How the system works: The heat pump takes energy from water to heat the gallery in winter. The system works in reverse in summer
The heat pump takes energy from water to heat the gallery in winter. The system works in reverse in summer