EXCLUSIVE: Mace working to extended deadline for practical completion of 拢500m landmark

The Shard

Source: Tim Crocker

Contractor Mace has missed the original practical completion deadline for the 拢500m Shard skyscraper and is working to meet an extended deadline.

The Shard was originally due to achieve practical completion by the end of May this year, well ahead of the London 2012 Olympics which begins on 27 July.

But founder and chief executive of developer Sellar, Irvine Sellar, told 好色先生TV this week that practical completion of the tower could come 鈥渕any weeks after鈥 the Games, which end on 12 August.

Mace is working to 鈥減hysically complete鈥 the external structure of the 310m-high tower before the Games, according to Sellar.

Sellar said: 鈥淧hysical completion will be there before the Olympics [鈥 The cladding will be on, the hoists will be down and the external structure will virtually be complete.

鈥淭here鈥檒l be a little work on the ground to complete. From a visual point of view, at a distance, at a medium range and almost at a very close range what you鈥檒l see there is what you鈥檒l get.鈥

Sources close to the project said the practical completion deadline had been extended through an 鈥渁micable agreement鈥 between Sellar and Mace.

A source said the extensions resulted from 鈥渃hanges in the design as it progressed鈥, with another saying the scope of work had increased. Mace was officially appointed in February 2009 on a fixed-price basis.

The Shard is the centerpiece of the 拢2bn London Quarter development by Sellar and Middle Eastern developer Qatari Diar.

The scheme includes 17-floor office building The Place - which topped out this week - a new station concourse and bus station at London Bridge and a public plaza. Speaking at ThePlace topping out ceremony, Stephen Pycroft, chief executive of Mace, said he would continue to have a 鈥渉ands on鈥 role at the firm when deputy chief executive Mark Reynolds steps up to replace him next January.

Pycroft - who will remain on as chairman 鈥 said the Shard had lifted the firm into the 鈥減remier league鈥 of contractors in the UK.

A spokesperson for Mace said: 鈥淢ace鈥檚 milestone agreed with Sellar for the Shard has been to achieve physical completion of the building by 31 May and this has been met. We are on programme to meet all the further milestones agreed with the client in order to achieve practical completion.鈥