The government intends to complete the procurement process for a typical secondary school in just over a year 鈥 roughly half the time needed for a typical hospital scheme.
Speaking at 好色先生TV鈥檚 鈥淯nderstanding the Education Sector鈥 conference this week, John Pilkington, Amey Ventures鈥 managing director, said a project should move from a notice in the Official Journal to financial close with a preferred bidder within 13 months.
The first projects in the 15-year Schools for the Future programme appeared in the OJ in September.
Pilkington has completed a secondment with Partnerships for Schools, the quango running the Schools for the Future programme.
He said: 鈥淲hat people haven鈥檛 grasped is the sheer scale of what is happening.鈥 He believes 140 schools a year will be rebuilt and a further 95 refurbished.
Bid costs for each scheme could be up to 拢1m for each Local Education Partnership, the public鈥損rivate framework that acts as a client for schemes.