Bosses blame 鈥榗omplexity鈥 of 拢80m Commonwealth Institute refurb
The Design Museum has pushed back the move to its new home at west London鈥檚 Commonwealth Institute following delays caused by the 鈥渃omplexity of the renovation鈥 of the Grade II* listed structure.
Currently based at Butler鈥檚 Wharf in south-east London, the museum was originally due to move to the 1960s-built modernist structure in 2014 after an extensive refurbishment masterminded by John Pawson Architects.
The opening of the 拢80m museum - which will see the creation of 10,000m2 of new space, including permanent-collection display areas, two temporary exhibition spaces, and a 192-seat auditorium - was subsequently pushed back to late 2015.
Now it has emerged that the Design Museum has agreed a six-month lease extension on its current premises 鈥 bought last year by Zaha Hadid Architects - kicking the move to the Commonwealth Institute into the second half of 2016.
A museum spokeswoman was unable to confirm a precise opening date for the museum at the Commonwealth Institute, but indicated autumn 2016 was now the target.
鈥淲e plan to close to the public [in Butler鈥檚 Wharf] in the summer of 2016, and there will then be a number of weeks for decanting and making good the building before we vacate it,鈥 she said.
鈥淭he opening date for the museum has moved a few times, we are now looking at 2016 although we do not have a confirmed month at this stage.鈥
She added: 鈥淭he move to a 2016 opening date is not the result of a particular problem with the project - it reflects the complexity of the renovation of a listed building.鈥
The museum鈥檚 current exhibition schedule includes events at Butler鈥檚 Wharf that run up to the end of June 2016.
Mace is main contractor for the Commonwealth Institute project - which has a total value of 拢105m because of three residential blocks included in the scheme - but declined to comment on the cause of the delay.
However, a source close to the project told 好色先生TV Mace was on course to hand over the Commonwealth Institute next month for fit-out work to begin.
The source described the delay as a 鈥渕inor鈥 one reflecting the 鈥渃omplex engineering challenge鈥 of the project, where 鈥淢ace wants to get the quality right, rather than rush and compromise鈥.
The museum鈥檚 most recent update on the progress at the Commonwealth Institute, issued last month, said all of the building鈥檚 floor slabs were now in place and work on the glass cladding installation for the exterior had commenced.
As , Mace was forced to deviate from original plans to demolish the building鈥檚 original slab floors from the second storey down and dig out a new basement area after it became evident that the strategy would not be a 鈥減rogramme friendly鈥 approach for prompt completion of the scheme鈥檚 residential blocks.
Instead the contractor opted for a top-down construction approach, which required more temporary work to prop up the whole building while the excavation took place, but allows the basement shared by museum and residential element to be completed earlier.
No comments yet