Contractor launches 拢3.6m counterclaim against cladding firm Prater, citing 鈥榙efective鈥 work and 鈥榙elays鈥
Galliford Try has hit back at cladding subcontractor Prater with a 拢3.6m counterclaim in the firms鈥 High Court battle over losses as a result of delays to the construction of the London 2012 athletes village.
Galliford Try lodged its defence and counterclaim with the High Court this month, in response to a 拢4.4m claim lodged against it by Prater in November.
Prater claimed Galliford Try 鈥減resided over a chaotic and shambolic site鈥, causing delays and losses to Prater. But in its defence and counterclaim Galliford Try contends Prater was responsible for its own delays and losses and further claims the subcontractor鈥檚 鈥渄elayed鈥 and 鈥渄efective鈥 work caused delays and losses for Galliford Try.
The claims relate to delays on the final two plots of the athletes village, N13 and N26, where Galliford Try was the main contractor. The plots were together worth 拢80m and comprised 14 blocks and 423 units, according to construction analyst Barbour ABI.
Prater, which says its contract was worth 拢11.3m, is the second subcontractor to lodge a High Court claim against Galliford Try relating to delays on the job, after concrete subcontractor Reddington filed a 拢6.8m claim against Galliford Try in the summer of 2012.
Galliford Try hit back against Reddington in November 2012 with a 拢7.7m counterclaim, alleging the delays were in fact caused by Reddington. That case is scheduled to be heard this June.
Galliford Try鈥檚 athletes village job hit delays from the outset, including a 19-day site shutdown to investigate an accident shortly after construction began in summer 2010.
Overall construction manager Lend Lease eventually handed over the two plots to the Olympic Delivery Authority six weeks late in December 2011.
In its defence and counterclaim, Galliford Try alleges Prater was responsible for delays to its own works after 鈥渄elays to the procurement of the [cladding] tiles鈥 and 鈥渇ailure [鈥 to install them regularly and diligently鈥.
Galliford Try denies Prater鈥檚 claim for loss and expense of 拢1m and accepts only 拢1.1m of the 拢4.3m the subcontractor claims for variations, with the contractor arguing that it in fact overpaid Prater for its works by 拢74,000.
In addition to this figure, Galliford Try claims 拢2.9m for delay and disruption costs, 拢363,000 for remedial works and 拢191,000 for contra-charges.
Galliford Try admits concrete subcontractor Reddington, whose work preceded Prater, handed over its works late, but denies this affected Prater鈥檚 ability to meet a revised and agreed schedule for its works because of the 鈥済reater delays in the procurement of the tiles鈥.
Galliford Try denies Prater鈥檚 claim that it ordered a 鈥渓ate change鈥 to install the facade from top down rather than bottom up and says the change was 鈥渞equested鈥 by Prater.
Galliford Try also argues it was 鈥渁lways [its] intention鈥 to allow internal trades to access the blocks via external temporary staircases and this did not delay Prater鈥檚 works, contrary to Prater鈥檚 claim.
The firm also denied Prater鈥檚 鈥渧ague and woolly criticisms of [its] management鈥.
Galliford Try and Prater declined to comment.
No comments yet