Concern comes as management of a repeatedly delayed 拢600m government framework for consultants is transferred to a private sector company

useful

The management of a repeatedly delayed 拢600m government framework for consultants has been transferred to a private sector company, prompting fears there could be further delays.

The Government Procurement Service (GPS), overseen by the Cabinet Office, said on its website late last month that private sector firm UK SBS had taken over management of the four-year Project Management and Full Design Team Services framework and two other government construction frameworks.

The consultant framework is currently being prepared for re-tendering after its last four-year iteration expired on 16 June.

The re-tendering has been pushed back several times, after originally being scheduled to go out in December 2012 so the framework could go live on 16 June to seamlessly replace the old one.

We are concerned about the move. It鈥檚 highly likely to cause more delay

Consultant source

Re-tendering was pushed back to 鈥淛uly or August鈥 in March and then to 鈥淥ctober or November鈥 in June.

The framework is now not due to be awarded, or to go live, until 鈥渆arly 2014鈥, according to the GPS website, at least six months after the previous framework expired.

Public sector clients that previously used the framework have been forced to procure work through OJEU or alternative frameworks during the hiatus period.

One consultant previously on the framework, who did not wish to be named, said: 鈥淲e鈥檙e concerned about the move [to appoint UK SBS]. It鈥檚 highly likely to cause more delay and brings into question whether the planned framework structure will be changed further.鈥

Another consultant said they were concerned the change in management would cause delays.

A further consultant, also previously on the framework, said he was concerned about the uncertainty as the framework had been 鈥渇antastic鈥 for his firm.

But he said the change may be welcome 鈥渋f a private sector company can come in and cut through the bureaucracy and get the tender out quicker [than GPS]鈥.

A Cabinet Office spokesperson said the move to hand management of the framework to the UK SBS would 鈥渟ave money and increase efficiency in procurement across the public sector鈥.

She said: 鈥淭imescales have not been affected by the move, and the Project Management & Full Design Team Services framework is expected to be available in early 2014.鈥