Testing of trains along the route started last week, six weeks after originally scheduled
Crossrail will renew its construction push next month to 鈥渃atch up鈥 on work paused during a delay in trial running of trains along the route.
The railway鈥檚 chief executive Mark Wild said in an Elizabeth Line committee meeting yesterday that the pause, termed 鈥渂lockade鈥 by Crossrail, will help the project speed up work that had been delayed.
It follows the official start of trial running last week, six weeks after the originally scheduled start date for the tests.
Four trains an hour are now running through the 拢18.6bn line鈥檚 central London tunnels to make sure that the route is safe and reliable.
Wild said that while the project 鈥渄idn鈥檛 achieve鈥 its aim to start the tests in late March, the beginning of the trials last week was two or three weeks ahead of the 鈥渞isk adjusted dates鈥.
He admitted that it had been a 鈥渃hallenging鈥 time and the project had learned 鈥渟o much鈥 in the process, and said that he believed trial operations are on track to start later this year.
Trial operations test the line鈥檚 ability to operate the railway, but cannot begin until all nine central London stations have been handed over to Transport for London.
Next month鈥檚 blockade will be the third on the project following a six-week push last summer to make up for time lost during covid-19 pandemic restrictions.
A second blockade, which paused train testing to allow for a period of round-the-clock construction, started in November last year to get the line ready for the next stage of testing.
Currently, only Farringdon, Custom House and Tottenham Court Road stations have been handed over.
In its latest monthly report, Jacobs said it had identified problems with four stations, Bond Street, Whitechapel, Paddington and Canary Wharf, for which 鈥渕itigation measures鈥 would be needed.
It raised particular concerns with the troubled Bond Street station, finding that 鈥渃oncessions may be required鈥 to achieve its delivery dates in time for trial operations.
Wild said in response to the report that he was confident that Bond Street would be ready since an assurance strategy had been drawn up with both London Underground and Crossrail keeping a close eye on the situation.
No comments yet