Japanese and German lenders pull plug on funds
Interserve has formally been binned from its last energy-from-waste project.
Its Resource Recovery Solutions (RRS) joint venture carrying out work on the plant at Derby was told on Friday afternoon that a contract between the team and Derby city and Derbyshire county councils had been terminated.
Banks funding the project issued a legal notice 鈥 called a No Liquid Market notice 鈥 pulling the plug on the scheme.
RRS, which also includes waste management specialist Renewi, signed a 27 year deal worth 拢950m with the local authorities five years ago which, as well as building the 拢145m plant at Sinfin (pictured), also included work to operate and manage nine household waste recycling centres and manage a further two waste transfer stations.
But Interserve, which has had sole responsibility for building the plant, has bust the original spring 2017 deadline and still not handed it over 鈥 despite entering the commissioning phase in January last year.
Now RRS鈥檚 consortium of Japanese and German lenders has said enough is enough 鈥 although the councils have asked Renewi to take a look at the plant to find out what needs to be done to make it fully operational.
READ MORE: Client drags more firms into Interserve Glasgow waste row
READ MORE: Kier woes deepen as British Land drops it for London job
Funding for the facility had been loaned to RRS by the UK Green Infrastructure Platform and Sumitomo Mitsui Banking Corporation and Shinsei Bank from Japan and Bayerische Landesbank from Germany.
Chris Poulter, leader of Derby city council, said: 鈥淚t鈥檚 clear to us that the contract with RRS has reached the end of the line so we鈥檙e not disputing this notice which formally ends the contract. But this does not mean the end of the project.
鈥淭hough it鈥檚 disappointing to have ended up in this position, we鈥檝e been preparing for the possibility of the contract coming to an end for some time now.鈥
At the end of last month the councils begun steps to replace RRS on the job.
The councils issued a Prior Information Notice alerting rivals to the 鈥減ossible end of [our] long term waste management contract with Resource Recovery Solutions鈥.
The Sinfin plant will stop accepting waste on a temporary basis but the councils have said it will be completed.
Chris Tyerman, director for infrastructure and engineering services at Interserve, said the firm was 鈥渄isappointed鈥 in the decision, which it believes has been made 鈥減rematurely鈥.
Renewi will now carry out work to find out its condition and capability while the same firm is also carrying out the deal to manage the waste recycling centres and transfer stations under a new two-year contract.
In June, Renewi told investors in its annual report that it has 鈥減rovided for the complete termination of the PPP contract鈥 because of 鈥渢he failure of our partner, Interserve, to commission the [Sinfin] facility鈥.
Renewi said this would mean a 鈧64m (拢57m) writedown of its investment in the facility and extra provisions for the costs of exiting 鈥 which it said were the biggest reasons why the firm lost 鈧98m (拢89m) in 2018.
And the firm also said it was owed 鈧11.6m (拢10.4m) by Interserve 鈥渂ut which remains outstanding鈥.
The plant has been dogged by a series of problems, including issues with the biofilter and the need to carry out remedial work on windows. Locals have also complained about smells and an infestation of flies.