Signalling Solutions鈥 鈥渕anagement processes鈥 to be reviewed by Network Rail after London Paddington closure
Network Rail will conduct a 鈥渢horough review鈥 of a Balfour Beatty and Alstom joint venture鈥檚 鈥渨ork management processes鈥 after an eight hour delay in its signalling work caused rail chaos over the Christmas period.
The joint venture, named Signalling Solutions, took nearly ten hours to complete a two hour safety check, which caused London Paddington station to close for most of 27 December.
The problems were one of two jobs that caused rail chaos over Christmas. Delays on a separate contract, being delivered by a joint venture of Amey and Sersa alongside Network Rail, caused London鈥檚 King鈥檚 Cross station to shut entirely on 27 December.
In the wake of the disruption the boss of Network Rail tasked staff with producing an urgent report into the causes.
That report, published today, found that some of Signalling Solution鈥檚 testing work on new signalling equipment installed at Old Oak Common, needed to be 鈥渞edone or rechecked鈥, causing delays to spiral and necessitating cancellation of services from London Paddington.
The report said Signalling Solutions had originally forecast that its safety checks would be complete by 3.30am on 27 December and it would take two hours to complete paperwork so the railway could be handed back to Network Rail by 7.00am.
But Signalling Solutions discovered testing work needed to be redone and paperwork was 鈥渋nconsistent鈥 and this resulted in the job running over until 1:14pm 鈥 nearly ten hours late.
The report said: 鈥淎 lack of warning that this work was delayed and frequent changes to the forecast completion time made it difficult to plan an effective train service.鈥
It revealed this was not the first time the joint venture had experienced a 鈥渟ignificant overrun鈥 on one of its projects. Its commissioning of a new signalling system at Poole had also overrun in May 2014.
The report said that Network Rail and Signalling Solutions would undertake a 鈥渢horough review鈥 of the contractor鈥檚 鈥渨ork management processes鈥 in the light of the most recent problems.
A spokesperson for Signalling Solutions said:
Meanwhile, it found disruption at King鈥檚 Cross was caused by 鈥渆quipment failures鈥 on the Switches and Crossings Northern Alliance contract, being delivered by a joint venture of Amey and Sersa alongside Network Rail.
The report said there were a 鈥渟uccession of equipment failures鈥 on the job which 鈥渦ltimately put the track renewal activities out of sync with their supporting engineering trains, stalling progress鈥. This caused the project to fall 15 hours behind schedule.
It also said there was 鈥渋nsufficient contingency鈥 in the project plan.
However, the report gave no indication that the Amey and Sersa joint venture will be subject to a similar review of its work management processes.
Mark Carne, chief executive of Network Rail, said he 鈥渦nreservedly apologised鈥 to passengers affected by the problems.
He said: 鈥淭he explanation is complex at some levels, but also simple.
鈥淚n very complex projects sometimes simple things go wrong and these can snowball in short periods of time to become major issues. Our contingency plans should address these issues and protect passengers from our problems as far as possible. And our industry service recovery plans should minimise the impact of any disruption once it has occurred.
鈥淥n these occasions we simply did not do these things well enough.鈥
Signalling Solutions and Amey have been contracted for comment. Sersa declined to comment.
No comments yet