Mr Justice Akenhead enforces adjudicator's decision, despite criticizing it for poor grammar and 鈥渦nconventional sentence structure鈥

Balfour Beatty has been awarded 拢1.4m after it launched a writ against Shepherd Construction to enforce an adjudication.

The row centred around a 拢65m development in Hull. Balfour Beatty Engineering Services - formerly known as Haden Young - was hired by main contractor Shepherd Construction to carry out M&E works on new facilities at Castle Hill hospital in April 2007.

In a writ filed at the High Court, Balfour Beatty claimed that Shepherd had deducted 拢2.2m from its payment after the subcontract works came in five months late.

However, on 2 July, an adjudicator ruled that the subcontract completion date should be extended to 10 June 2008, and that Shepherd was not entitled to deduct the costs. Shepherd was also ordered to cover the adjudicator's fees and expenses which, added to the other sums, totalled over 拢1.4m, plus interest and costs.

Commenting on the adjudicator's ruling, Mr Justice Akenhead said the decision 鈥渨as no work of art鈥, and criticized the judgment for its poor grammar and 鈥渦nconventional sentence structure鈥.

But he ruled that the adjudicator's decision should be upheld, though he said Hayden Young's claim of 拢78,000 in costs was 鈥渄isproportionate鈥 to the proceedings, ordering Shepherd to pay 拢45,000 in costs instead.