Campaigners against planning deregulation want to see new rights quashed

The Court of Appeal will rule next week on a legal challenge aimed at quashing the government鈥檚 expansion of permitted development (PD) rights to create new homes, which was pushed through in the wake of the pandemic lockdown during the summer.

The court has scheduled 5 October to consider an appeal by environmental campaign group Rights: Community: Action (RCA) of last November鈥檚 High Court dismissal of its claim that new development rights were not properly considered or consulted on before being brought in.

terminushousebestone_136178

In August the housing ministry - now the Department for Levelling Up, Housing and Communities (DLUHC) - introduced new PD rights via statutory instrument. These allowed developers to demolish and rebuild properties as homes, to build new homes above existing homes and offices, and removed a raft of previously existing planning use classes.

The moves, which were billed as part of the government鈥檚 response to the economic crisis brought on by the covid-19 pandemic, were bitterly opposed by many planners and came despite evidence of the poor quality of homes built under existing PD rights.

The changes were also introduced without a further consultation that the government had promised when the majority of respondents to an earlier consultation on the same proposal were opposed to the plans.

Naomi Luhde-Thompson, director at RCA, said that if the challenge was successful it would result in the PD rights being quashed. 鈥淲e think this is really significant case,鈥 she added. 鈥淚t鈥檚 about defending the extent of protection provided by environmental protection laws in England.鈥

The new PD rights were last year described as 鈥渄isgraceful鈥 by the RIBA, given concerns over the quality of new homes approved under the process, such as Terminus House in Harlow (pictured, right). Last July the government received a rare joint rebuke over the changes from the professional institutions governing much of construction and development 鈥 the RIBA, the Royal Town Planning Institute, the Chartered Institute of 好色先生TV and the RICS.

The government鈥檚 好色先生TV Better 好色先生TV Beautiful Commission last year said the existing expanded use of PD had inadvertently permitted 鈥渇uture slums鈥, while the government鈥檚 own assessment of the quality of homes produced by PD said they created worse homes 鈥渋n relation to a number of factors widely linked to the health, wellbeing and quality of life of future occupiers鈥.

However, last November, High Court judges Lord Justice Lewis and Justice Holgate ruled against RCA鈥檚 challenge on all three grounds raised by the charity. However, they conceded that the first of RCA鈥檚 grounds 鈥 whether the government should have carried out a strategic environmental assessment (SEA) before bringing in the new statutory instruments 鈥 was arguable and granted RCA leave to appeal.

RCA鈥檚 grounds of appeal document alleges that the High Court 鈥渆rred in concluding that the three statutory instruments were not required to be subject to strategic environmental assessment鈥.

The High Court judgment found the statutory instruments did not 鈥渟et the framework for future development consent of projects鈥, and therefore could not be subject to an SEA under existing law. However, RCA is set to argue that this judgment relies on an 鈥渦nduly narrow construction of the term 鈥渄evelopment consent鈥.鈥

Official figures show the government鈥檚 prior expansion of PD rights, introduced in 2014, had produced almost 73,000 new homes up to March 2020.

A spokesperson for DLUHC said: 鈥淲e are aware of the legal proceedings. We do not comment about ongoing litigation.鈥