The story of the Spitalfields development
Bishops Square marks the culmination of 19 years of development of Spitalfields on the eastern fringe of the City of London. The fact that it has taken 19 years to regenerate just 5 ha of land speaks of the development鈥檚 intensely controversial nature. Disputes were mostly thrown up by the site and its location on the faultline between Europe鈥檚 financial centre and the underprivileged East End. Added to that were major issues of architectural conservation, extensive archaeological remains and, not least, radical changes in the financial sector, which powered the whole development. Here鈥檚 how two decades of wranglings unfolded 鈥
May 1986: Site for sale
Corporation of London puts the 5 ha site around Spitalfields market up for sale in an effort to compete with Docklands in housing London鈥檚 exploding financial sector.
September 1987: SDG wins site bid
Spitalfields Development Group, a consortium that includes contractors Balfour Beatty and Costain, wins the site acquisition tender over Rosehaugh Stanhope and Priest Marians, largely because it had already acquired a site in Hackney Marsh for relocating the wholesale market. Its 拢200m, 163,000m2 scheme, which is designed by MacCormac Jamieson Prichard & Wright and Fitzroy Robinson & Partners with large office buildings in a traditional street pattern, wins planning approval from Tower Hamlets. Completion is set for 1994.
October 1987: An alternative scheme
Conservation watchdog Save Britain鈥檚 Heritage commissions a rival scheme that recreates the former Spital Square.
January 1989: New architects 鈥
Swanke Hayden Connell designs a more flexible scheme, working with MacCormac Jamieson Prichard & Wright, Hunt Thompson, Allies and Morrison, Edward Cullinan Architects and Pollard Thomas & Edwards.
August 1989: 鈥 and more architects
Colquhoun & Miller, Ian Ritchie, Burrell Foley and Santiago Calatrava are all appointed by SDG to work with Swanke Hayden Connell, after the previous architects fall out with Swanke Hayden Connell and resign.
May 1991: New masterplanner
American urban designer Ben Thompson Associates is appointed masterplanner to work with EPR Architects, after Swanke Hayden Connell鈥檚 scheme is called in for review by the Department of the Environment. Thompson divides the site into 14 medium-rise buildings, each to be designed by a different architect.
March 1991: Veg market relocates
More than 1000 wholesale fruit and vegetable traders relocate to new market buildings in Hackney Marsh developed for 拢50m by SDG.
February 1992: Spitalfields market reopens
While the property market tumbles, SDG reopens the market building as a general retail market with up to 330 stalls attracting 10,000 people every Sunday.
June 1992: Foster鈥檚 first scheme rejected by planners
Foster and Partners鈥 first Spitalfields design, a 16-storey tower on Bishopsgate, is rejected by the Corporation of London as it threatens views of St Paul鈥檚 Cathedral.
April 1992鈥揗arch 2004: Public鈥損rivate regeneration
SDG chief executive Mike Bear is appointed vice-chairman of Bethnal Green City Challenge and one year later is promoted to chairman. After 1997, SDG contributes to succeeding regeneration companies, Cityside Regeneration and City Fringe SRB. Over 12 years, these three companies create more than 4300 jobs and 600 businesses, build 495 social homes and refurbish 1665 existing homes.
1992: Planning gains by SDG
Tower Hamlets develops 118 social homes and a sports centre in east Spitalfields funded by 拢3.75m planning gain from SDG. Total planning gains provided by SDG amount to 拢26m. 鈥淵ou have to listen to local people,鈥 says Bear. 鈥淭heir main agenda is jobs, housing and education.鈥
1993: Masterplan gains planning consent
The Thompson mixed-use masterplan for the 5 ha site, including 100,000 m2 of offices, is granted outline planning approval by Tower Hamlets council.
1998鈥2004: Archaeological digs
Intensive archaeological digs are carried out on cleared site by 100 staff from the Museum of London Archaeology Service, with 拢4m support by SDG. Some 25 medieval buildings, including the hospital that gave the district its name, are unearthed 鈥 along with 10,600 skeletons including the well-preserved remains of a rich 鈥淩oman lady鈥 from circa 350AD.
1998: First office building completed
ABN Amro bank moves SDG鈥檚 first office building at 250 Bishopsgate, designed by EPR Architects.
1998: Private housing development
SDG in joint venture with St George develops a classical brick terrace of 187 houses on Folgate Street facing the conservation area.
August 1999: Foster鈥檚 second scheme rejected by Liffe
Foster and Partners鈥 second Spitalfields scheme, a 拢200m 12-storey futures exchange, wins detailed planning permission but is abandoned when client Liffe switches from open outcry to electronic trading.
January 2000: Second office finished
SDG completes its second office building, a 拢46m, 2300 m2 serviced office building at 288 Bishopsgate, designed by Foggo Associates.
October 2001: Third office completed
Royal Bank of Scotland moves into SDG鈥檚 third completed office building, a 拢111m, 13-storey 250,000 m2 tower at 280 Bishopsgate designed by Foggo Associates.
March 2001: In comes Hammerson
Property group Hammerson completes takeover of SDG.
June 2001: Foster appointed for third scheme
Foster and Partners is appointed by SDG to design 拢250m mixed-use Bishops Square development of offices, retail and public spaces with Allen & Overy as office tenant.
November 2001: Alsop submits counter-proposal
Protest group Spitalfields Market Under Threat commissions a counter-proposal from Will Alsop, in which a 92,000 m2 office building is raised on stilts, leaving the market intact.
January 2002: Foster design panned
Foster鈥檚 revised design for Bishops Square is criticised by CABE for its 鈥漵ki-slope鈥 shapes.
November 2002: Bishops Square gains planning consent
Foster鈥檚 second design revision for Bishops Square, for a 108,000 m2 mixed-use scheme, wins detailed planning approval from Tower Hamlets council. SMUT pans Foster鈥檚 scheme as 鈥渢he imposition of a characterless corporate environment on a successful local diverse sustainable community that is of equal importance to the success of London as a 鈥榳orld city鈥欌.
September 2005: Bishops Square completed
The Bishops Square 拢285m mixed-use development is completed by Sir Robert McAlpine to Foster and Partners鈥 design.
And coming soon 鈥
November 2005: Market building refurbished
A mezzanine cafe floor in the market building designed by Lyons Sleaman Hoare is being developed by Ballymore, which bought the building in 1999.
December 2006: Lawyers move in
Allan & Overy to move 4000 legal staff into Bishops Square after completion of fit-out.
2007: Final Spitalfields developments
SDG鈥檚 final developments include the redevelopment of a 1920s ancillary market building by Scott Brownrigg, and a small hall behind St Botolph鈥檚 Hall.