Reference
The employer argued that clause 2.3 of the amended contract provided the employer with the right to set-off liquidated damages from any sum due under the contract. The employer maintained that this included sums due under an adjudicator's decision, which in turn was based upon the contractual provisions. Reliance was placed upon Bovis Lend Lease Limited vs Triangle Developments Limited" (2nd November 2002). On the other hand, the contractor argued that the contract should be interpreted to give effect to the adjudication provisions, and accordingly no set-off against an adjudicator's award should be allowed following the Court of Appeal case of Levolux AT Limited v Ferson Contractors Limited [2003] EWCA Civ 11 CA. HHJ Hull QC held that clause 2.3 of the contract did not provide a party with the right to set-off liquidated damages against an adjudicator's decision. He followed the Court of Appeal in Levolux considering that the approach in Bovis had been disapproved by the Court of Appeal.
For further information, call Tony Francis or Nicholas Gould on 0207 956 9354
Postscript
It is clear that the courts will now follow the Court of Appeal's ruling in Levolux and enforce an adjudicator's decision in preference to the contractual provisions providing for set-off. This reinforces the view that a respondent to an adjudication, that considers that it has a cross-claim must commence a cross-adjudication if it is to have any chance any defeating the enforcement of an earlier adjudicator's decision. Many thanks to Brent McDonald of 2 Temple Gardens for supplying details of this case.