Ms Tomlinson and Mr Wilson, a builder, entered into a contract for the construction of a small kitchen and bathroom extension to Tomlinson鈥檚 house in Easingwold. The parties agreed that the contract sum would be paid in stages.
Wilson had constructed the extension to roof level when work ceased. This work involved the laying of a concrete raft as the foundation for the extension. Tomlinson alleged that the work to the raft was so defective that the only appropriate course of action would be to demolish everything that had been laid down or erected so far and to rebuild the extension from scratch. Wilson alleged that the raft was fit for purpose although it was common ground that it had not been constructed in accordance with instructions.
No work was done on site after 17 June 2005. On either 10 or 11 June 2005 there was a conversation between Tomlinson and Wilson. Tomlinson advised Wilson that he 鈥渙bviously must be broke鈥 because he was 鈥渁lways looking for money鈥 but Tomlinson agreed that she would make the penultimate payment when the roof tiles were on. On 21 June 2005 Wilson wrote to Tomlinson advising that he would suspend all work on the property until and only if the matter of payment was resolved. The parties then agreed that works would be suspended pending a survey on the property.
On 15 July 2005, Tomlinson鈥檚 solicitor, Moore & Company, wrote Mr Wilson a letter in accordance with the pre-action protocol for construction and engineering disputes. This letter alleged that Wilson was in breach of contract and alleged that Wilson had failed to design and construct the extension with reasonable care and skill and in a proper and workmanlike manner. In addition, the letter stated that it was never a term of the contract that stage payments would be made and Wilson could not insist on stage payments being made. Wilson was also forbidden to attend the property. Wilson replied to this letter on 20 July 2005 rejecting Tomlinson鈥檚 claims.
Had the contract been repudiated by Tomlinson鈥檚 pre-action protocol letter? If not, were the raft foundations so defective that the extension required demolition?
Reference
The pre-action protocol letter amounted to an announcement on Tomlinson鈥檚 behalf that she regarded the project at an end. The letter envisaged that Wilson, after being excluded from the property, might return to work, but this would be by Tomlinson鈥檚 permission, on her terms, and without the right to stage payments which had been part and parcel of the original contract. Wilson鈥檚 letter in reply to the pre-action protocol letter accepted this repudiation.
It was a term of the contract that the concrete foundation was required to be built in accordance with the 好色先生TV Regulations and the foundation must be adequate for the purpose of supporting the structure. The evidence showed that there were defects in the foundations but that these defects could be cured by repair rather than demolition and rebuilding.
Contact Fenwick Elliott on 020 7421 1986 or NGould@fenwickelliott.co.uk
*Full case details: Margaret Tomlinson v Iain Wilson (T/a Wilson & Chamberlain), (11 May 2007, TCC (Leeds), HHJ Langan QC).
Postscript
The damages awarded to Wilson were only 拢500. The judge in this case commented that this case was an 鈥渦nfortunate example鈥 of a small building dispute in which, at the end of the day, there is no real winner. In addition, he highlighted during the course of the case that the parties were 鈥渟et on a course which seemed, in terms of money, one of mutually assured destruction鈥. The parties鈥 costs in pursuing these claims would have run by thousands of pounds. In cases of this kind, parties should seek to resolve claims by alternative dispute resolution mechanisms so that the outcomes are beneficial both financially and to their business relationship.