There are still many lessons that need to be learnt from Crossrail, writes Caroline Pidgeon

On 21 August the latest announcement from Crossrail brought news that the central section of the project between Paddington and Abbey Wood would be further delayed until the 鈥渇irst half of 2022鈥, with trial running starting at the 鈥渆arliest opportunity in 2021鈥. 

As Crossrail鈥檚 first opening date was December 2018, the project is now 3.5 years behind schedule. 

caroline pidgeon

The project is seriously over budget as well. The latest cost estimate presented to Crossrail鈥檚 board is that the project could be up to 拢1.1bn above the upward revised financing package agreed in 2018 and 拢450m more than the upper end of the range announced in November 2019. 

We are supposed to be reassured that 鈥渨ork is ongoing to finalise the cost estimates鈥. The reality is that in any construction project, time is money. If there is any further slippage there will inevitably be further increases in costs.

鈥淭he reality is that in any project, time is money. If there is any further slippage there will inevitably be further increases in cost.鈥

In fact, the true cost of Crossrail goes much further than its construction costs. By eating into money that had been put aside for other transport projects, it is leading to many TfL schemes being put back or cancelled. The delayed opening date is also leading to TfL being denied valuable fare income and other sources of income from advertising and commercial rent at stations.

New Crossrail budget and timeline waiting on approval 
Caroline Pidgeon: A decade spent scrutinising Crossrail  
Crossrail costs to top 拢19bn as bosses confirm 2022 opening

For Tube users the delays postpone the opportunity to relieve pressures on significant sections of the Tube network, especially the Central line. 

Just how could so many things go wrong with this flagship scheme?

In May 2019 the National Audit Office鈥檚 report into Crossrail concluded that: 鈥淭he compressed schedule, the contractual model, the loss of downward pressure on costs, and the absence of a realistic plan were set against an atmosphere where 鈥榗an do鈥 became unrealistic.鈥

What they were picking up on was what the London Assembly transport committee had already discovered. A month earlier we published a report with the following main findings:

  • E-mails between Crossrail and TfL suggested that communications to the mayor were watered down by the TfL commissioner, instead of flagging risks to the timetable earlier.
  • Significant concerns raised by the independent reviewer, as early as January 2018, were largely ignored.
  • The desire to achieve the completion date overpowered any professional and critical assessment of risk.
  • The Crossrail executive did not have the skills required at the later stages of the project to adequately assess risks as they became apparent

Our key recommendations were:

  • TfL鈥檚 commissioner (then Mike Brown) must reflect on whether he is fit to continue to fulfil his role in TfL.
  • The mayor and TfL board must strengthen control over TfL and implement the necessary processes to allow them to remain fully informed and on top of the projects they are ultimately accountable for.
  • Crossrail should have systems that encourage transparency, openness and a sense of accountability at all levels.

It would be totally unfair not to give credit to changes that have occurred in the last two years. However, I still feel many lessons need to be learnt. 

It is concerning that on the 19 August 2020, the mayor of London can write to me saying that we are 鈥渘earing the point when the railway can enter full testing and trial running鈥. Yet two days later Crossrail announce they cannot give a precise date as to when such testing will start in 2021.

It is also hard to understand why the chair of Crossrail, as recently as June of this year, was telling the TfL board that he thought Crossrail would 鈥渕eet or beat鈥 the then opening date of summer 2021.

Crossrail鈥檚 board still meets in private, unlike the TfL board. And while the independent consultant reports by Jacobs are published they are heavily redacted and their publication online frequently delayed.

I continue to be a strong advocate of Crossrail and I hope in just a few years鈥 time we are enjoying its immense benefits, and its delays are a distant memory for passengers. However, anyone involved in public policy cannot deny that such severe delays and increased costs do have long-term consequences. It is precisely because I wish to see more large-scale infrastructure projects that I am so keen that we learn all the lessons from the mistakes over Crossrail.

Carolyn Pidgeon is a Liberal Democrat London Assembly member and the assembly鈥檚 transport committee deputy chair