Here鈥檚 a curious story in which the drafters of a contract tried to save a little time and paper, and ended up fundamentally changing the nature of the agreement
A decision by the Technology and Construction Court in Bristol just before Christmas has serious consequences for many contracts in the power and water industries.
As we know, UK construction contracts are subject to part two of the Construction Act 1996. That legislation has a lot to say about payment provisions in contracts, and adjudication as a method for resolving disputes. Of course, for the act to apply, the contract has to be a 鈥渃onstruction contract鈥 as defined by the act. If the contract is not within that definition, the act has no relevance.
But parties can agree to apply provisions of the act to their contract, even if not obliged to do so. For example, the parties can adopt adjudication as the system for resolving disputes. This is often the case in contracts with residential occupiers or contracts for works in power stations that fall within the statutory exceptions.
JCT contracts are an example. Article seven of the standard form says that either party may refer a dispute to adjudication, whether or not the works are covered by the act. The contracts incorporate the Scheme for Construction Contracts, which is a template for adjudication, and takes much fewer pages of drafting than setting out all the detailed procedures for adjudication.
Many 鈥渙ne off鈥 contracts often adopt a similar approach. That was the position in the contract that gave rise to the decision in December. RWE Npower contracted with Alstom Power for the repair and maintenance of the boilers at Aberthaw power station in the Vale of Glamorgan. The works overran and claims were made by the contractor for extra costs of more than 拢1m. RWE, on the other hand, made claims for liquidated damages for delay. Alstom took its claim to adjudication under a term of the contract which, like the JCT clause, imported the Scheme.
Alstom was partially successful in the adjudication, and obtained a decision that RWE should pay 拢220,000. RWE then sought to set off its claim for liquidated damages, which was substantially greater than the sum due under the decision.
This would not have been possible if the contract were subject to the Construction Act. Section 111 says there can be no set off against a sum due without a withholding notice. RWE had not served a withholding notice, but on the basis that the contract was not subject to the act, that did not seem to matter.
RWE therefore declined to pay on the basis that it had a good claim for liquidated damages that was substantially greater than the sum the adjudicator thought was due to Alstom. There were other quite different grounds for argument as well, which involved consideration of jurisdiction and natural justice. RWE decided not to wait for an application to the court to enforce, but made the first move by applying for a declaration that the decision was unenforceable.
The result was not what RWE expected, even though Alstom agreed that for the purposes of the application it could be assumed that the contract was not subject to the act. Judge Havelock-Allan concluded that 鈥渂y choosing to incorporate the provisions of the Scheme rather than their own bespoke provisions for adjudication, the parties intended to import into the contract the parliamentary intention underlying the Scheme鈥. He decided that the parliamentary intention was that adjudicators鈥 decisions should be paid without any set off. If you adopt the Scheme with regard to adjudication procedure, you adopt all the other features of the act with regard to payment, including the requirement for a withholding notice.
This came as a shock to RWE, but also to those involved in the preparation of non-standard contracts not automatically subject to the act. Many contracts involving work in power stations, sewage treatment plants and the like incorporate adjudication clauses and for the sake of certainty and simplicity adopt the Scheme, as do JCT contracts. This judgment suggests that by doing so they unwittingly incorporate all the rules relating to payment (including inability to set off without withholding notices), that they assumed did not apply.
Curiously, if the contract had set out verbatim all the contents of the Scheme relating to adjudication, without actually referring to 鈥渢he Scheme鈥, the 鈥減arliamentary intention鈥 would have been completely irrelevant and so would the payment provisions of the act. Economy of drafting has produced a big surprise.
John Redmond is head of construction at Osborne Clarke