Ted Lowery considers a claim for defective piling equipment
The case
MG Construction Ltd vs AGD Equipment Ltd [2020] ScotCS CSOH 72
Opinion of Lord Ericht
In the Outer House, Court of Sessions
Opinion delivered 14 July 2020
The facts
During July 2014 MGC purchased a piling rig from AGD consisting of an impact hammer and a piece of equipment known as the 鈥渓eader鈥 which acted as a guide for the hammer and maintained verticality during piling.
In May 2015 MGC鈥檚 foreman noticed a paintwork blemish on part of the leader known as the 鈥渞am box鈥 and asked MGC fitter Mr Jack to carry out an inspection. Mr Jack produced a report dated 12 May stating, 鈥淣oticed small crack in paintwork on side shift ram box section. Applied weld to crack for visual check.鈥
On 17 May 2015 during works at a site in Edinburgh the ram box broke in two and the piling rig collapsed. It was apparent the ram box had sheared along the line of a pre-existing circumferential crack that had been repaired by welding and painted over: the welding had been poorly executed but expertly concealed. AGD agreed to replace the rig but without any admission of liability. MGC retained but subsequently lost the smaller section of the broken ram box.
MGC contended the weld must have been made prior to purchase so that the piling rig was not of satisfactory quality, contrary to section 14 of the Sale of Goods Act 1979. MGC commenced proceedings seeking damages including lost profits and settlement monies paid to the main contractor. In reply AGD denied that there had been any welding prior to purchase and suggested an alternative scenario whereby misuse of the rig had caused metal fatigue that MGC had sought to remedy by carrying out welding repairs shortly before the failure on 17 May 2015. AGD further submitted that having chosen not to suspend piling operations following Mr Jack鈥檚 inspection on 12 May, MGC had failed to mitigate its loss and/or broken the chain of causation.
MGC presented factual evidence from its personnel that there had never been any recorded misuse of plant in 28 years, that equipment was regularly inspected and that any damage to the piling rig would have been reported. MGC also relied upon expert opinion evidence from paint technicians and a metallurgist, whose collective view was that unless the entire unit had been repainted after delivery, the ram box had been purchased with the weld in place. MGC鈥檚 factual witnesses did not include Mr Jack, who was apparently working offshore in South Africa and had declined to assist.
AGD鈥檚 factual witnesses included representatives of the piling rig manufacturer, who confirmed factory quality control procedures, and its own managing director, who said that in his experience, using the leader to straighten up embedded piles was common practice and would have weakened the ram box.
The issue
Had MGC proved its case that the weld had been made before purchase in July 2014, and if so had it failed to mitigate and/or broken the chain of causation?
The decision
The judge stressed the onus was not on AGD to demonstrate the plausibility of its alternative scenario, rather that in order to succeed MGC had to prove its case on the balance of probabilities.
The judge noted the absence of any direct evidence as to when the weld was carried out. He characterised MGC鈥檚 failure to call Mr Jack or to apparently take any steps to obtain evidence from Mr Jack by alternative means, for example video link or deposition, as creating a 鈥渇undamental difficulty鈥 for the claim. The judge considered that the expert evidence was inconclusive where the experts had not been able to examine the smaller section of the broken ram box. The judge concluded that the evidence on both sides was largely circumstantial and as such was insufficiently persuasive. Accordingly he dismissed the claim on the grounds that MGC had failed to discharge the burden of proof.
Commentary
The parties agreed that the failure of the ram box was caused by the poor quality of the weld but the dispute concerned when the weld had been undertaken. While the volume of evidence presented was considerable, MGC鈥檚 case was undermined by its failure to make available Mr Jack and the missing section of the ram box.
The judge observed that no tribunal would choose to determine disputes solely by reference to burden of proof arguments if it could legitimately avoid it but he reluctantly concluded that MGC鈥檚 claim was one of those unusual cases where, owing to the unsatisfactory state of the evidence, this approach was the only just course to take.
Ted Lowery is a partner in Fenwick Elliott
No comments yet