In the first in an occasional series focusing on individual cases, we report on a classic case of contractual uncertainty
The case
Malcolm Goldsworthy, Graham Goldsworthy & Paul Goldsworthy (t/a Goldsworthy Builders) vs John Harrison & Catherine Harrison. Before Mr Andrew Bartlett QC sitting as a deputy high court judge in the Technology and Construction Court. Judgment delivered 1 July 2016.
The facts
In 2012 Goldsworthy Builders submitted a number of quotations for works to the home of Mr and Mrs Harrison. Goldsworthy started work in late October 2012. During November 2012 and January 2013 the contract administrator (CA) appointed by the Harrisons referred Goldsworthy to the possibility of entering into a JCT Minor Works form of contract. In February 2013 Goldsworthy drew together its previous quotations and proposed a total price of 拢526,689.21, plus VAT. Work continued with Goldsworthy submitting invoices at the end of each calendar month.
On 22 October 2013 the CA issued a JCT Intermediate form of contract. Goldsworthy responded that it had tendered on the basis of the Minor Works form. The CA replied that the Minor Works form should be used but on 19 November 2013 proposed different payment terms - that he would issue a certificate within seven days of Goldsworthy鈥檚 valuation with the Harrisons paying within 14 days.
In January 2014 the CA issued a complete draft Minor Works form which included LADs and a defects rectification period of 12 months for the M&E works. Goldsworthy refused to sign and stated that it wished to continue the ad hoc arrangements set out in the CA鈥檚 email of 19 November 2013.
On 17 June 2014 the CA issued a certificate of practical completion which required the Harrisons to pay the amount certified on 20 May 2014 and half of the retention, 鈥渁s set out in the JCT Minor Works Contract鈥. Goldsworthy said its original quotations for the works formed the basis of the contract, not the Minor Works form. In March 2016 Goldsworthy commenced adjudication claiming payment of the amount certified on 20 May 2014 and the first half of the retention. On 22 March 2016 the CA issued a final certificate which showed a sum due to the Harrisons. In reply, on 24 March Goldsworthy issued a payless notice and a final account valuation which showed it was due 拢8,661.46.
Having rejected the Harrisons鈥 submission that because they had never agreed to the Minor Works form and were residential occupiers, there was no enforceable adjudication agreement, the adjudicator issued a decision on 17 April 2016 in favour of Goldsworthy.
On 24 May 2016 the CA issued a revised final certificate showing just over 拢5,000 due to Goldsworthy. On 25 May 2016 Goldsworthy commenced enforcement proceedings. Goldsworthy argued the Minor Works form had been fully incorporated into the contract and relied on the parties鈥 conduct, including that the CA had referenced the Minor Works form on interim certificates and followed the Minor Works form mechanisms for retention, completion and the final certificate. The Harrisons said no final agreement had been reached on the form and the works had proceeded under an informal agreement with no adjudication clause. They also said the adjudicator had no jurisdiction to decide a dispute on interim payments that was overtaken during adjudication by the issue of a final certificate.
The issue
Were the grounds advanced by the Harrisons sufficient to block enforcement of the adjudicator鈥檚 decision?
The decision
In rejecting the second ground the judge noted that if a final certificate was issued during an adjudication then depending on what the adjudicator had been asked to decide, the final certificate might have to be taken into account, particularly if unchallenged. Here, where Goldsworthy had immediately disputed the CA鈥檚 figures the adjudicator was entitled to attach little weight to the final certificate dated 22 March 2016. The judge also found that Goldsworthy鈥檚 24 March valuation did not negate or reduce the claims it had advanced in the adjudication.
Regarding the first ground, the judge reviewed the exchanges and noted there were a number of evidential gaps, with emails missing and phone conversations not accurately recorded. He said the evidence that was available was equivocal so that, for example, fixing retention at a commonly applied 5% was not determinative of the application of the Minor Works form. The judge also thought that references in the exchanges to the Minor Works form were too fragile a basis for a definite finding. Therefore he found it impossible to say that there was not a triable issue on the question of whether or not the parties did at some stage come to agreement as to the application of the Minor Works form and he declined to enforce the adjudicator鈥檚 decision.
Commentary
The issue of the final certificate will rarely have any bearing on adjudications which usually take place during or shortly after completion of the works. Albeit unusual, the circumstances of this case reinforce the importance of promptly challenging the final certificate.
Otherwise, this case is a classic example of what can go wrong when there is prevarication over the contract terms: it was only when disputes arose that each party began to scrutinise the earlier exchanges and, as the judge noted, in the adjudication and in court, each party advanced a case directly contrary to their previously stated positions.
As happened here, contractual uncertainty may create particular problems for builders working with residential occupiers. In the absence of a written contract that includes an express adjudication clause, adjudication will not be available.
Ted Lowery is a partner in Fenwick Elliott
No comments yet