Before Mr Justice Coulson. Judgement delivered 31 July 2015

Matthew Simson

The Facts

During April 2014 Topevent Ltd engaged Wycombe Demolition Ltd to carry out demolition works at a site at Lane End, Wycombe. It was common ground that there was an oral construction contract between the parties, but the date on which the contract was made and the relevant terms of the contract were disputed.

On 26 February 2015 Wycombe commenced an adjudication under the TeCSA rules claiming payment of outstanding invoices - which it sought to increase through a re-valuation - as well as damages in lieu and damages for breach of contract by Topevent for alleged wrongful termination.

In its response Topevent counterclaimed 拢180,000 contending that Wycombe had left substantial works incomplete and was in breach of contract for wrongful termination. Topevent also challenged Wycombe鈥檚 valuation of variations, extra works, and sums contractually due and requested that the adjudicator visit site in order to complete his assessment of any re-valuation.

The adjudicator refused Topevent鈥檚 request for a site visit, which he considered neither necessary nor cost-effective for making a determination of the value of the works. In his decision of 22 April 2015 the adjudicator found that the parties had 鈥減robably ended the contract by mutual consent鈥 and that the re-valued increased amount claimed by Wycombe was justified. The adjudicator awarded Wycombe 拢114,000 plus costs, and dismissed Topevent鈥檚 counterclaim.

Topevent did not pay and Wycombe subsequently issued enforcement proceedings in the TCC.

Topevent resisted enforcement on three grounds, that the adjudicator:
(i) lacked jurisdiction as he had determined multiple disputes
(ii) had acted in breach of natural justice by refusing to visit site
(iii) had acted in breach of natural justice by deciding the valuation on a basis that had not been advanced by either party.

The Issue

Should enforcement be declined on any of the grounds advanced by Topevent?

The Decision

As regards the multiple disputes point the judge observed that the notice of adjudication made it clear that the dispute between the parties concerned the outstanding payment due to Wycombe following the cessation of works on site. Both elements of the payment said to be due, those being the value of variations and the financial consequences of termination and demobilisation, were part of the same dispute - they were simply different components of the total sum in dispute. The judge therefore rejected this ground.

The judge also noted that in any event, the TeCSA rules provide at paragraph 11.1 that the adjudicator can deal with 鈥渁ny further matters鈥 which the parties agree should fall within the scope of the adjudication. If there were two separate disputes, Topevent鈥檚 acquiescence in, and failure to object to, the adjudicator dealing with both disputes gave the adjudicator the necessary jurisdiction.

The judge also rejected Topevent鈥檚 argument - described as 鈥渉opeless鈥 - that the adjudicator had breached the rules of natural justice by refusing to make a site visit. The judge said that it was for the adjudicator to decide what he must do in order to reach his decision, and in this case, the adjudicator had carefully explained why a site visit was not a proportionate use of his time or cost-effective. The judge also noted that a site visit would have been of no assistance to the adjudicator in valuing the works and variations, and that no submissions to the contrary had been made.

In rejecting Topevent鈥檚 third ground, the judge noted that the adjudicator was 鈥渇aced with a myriad of different approaches to valuation鈥 complicated by the unhelpful way in which the claims were set out. Having reviewed the submissions in the adjudication the judge concluded that the adjudicator had looked at the muddled claim documentation and the even more muddled response, and then considered the evidence including the witness statements and come to a conclusion. The adjudicator had not strayed beyond the boundaries of natural justice by either making good the deficiencies in the claiming party鈥檚 case or by plugging a gap in that case without prior notice to the parties.

Commentary

This decision should provide some comfort to adjudicators confronted, as they frequently are, with opaque claims and incoherent evidence. The judge stated that the adjudicator has to do his/her best with the material provided and has considerable latitude to reach his/her own conclusions based on that material without being bound to accept the figures advanced by the parties.

The judge also expressed the view that this latitude will be wider now that adjudication can encompass contracts not recorded in writing. As happened here, the adjudicator鈥檚 conclusions about the nature and terms of the contract could affect his/her approach to valuation issues.

Matthew Simson
Fenwick Elliott LLP