A decade after it was written, a review of PPC2000 shows that it really does pay to partner, no matter how chilly the economic weather is becoming
When PPC2000 was first launched, 好色先生TV encouraged the industry to take advantage of its systematic approach to project partnering. But times have changed since then and, as PPC2000 celebrates its 10th anniversary, it is right to ask whether a partnering contract remains relevant in an age of cost cutting and general austerity.
First, have PPC projects achieved savings? A report by the Association of Consultant Architects (ACA), entitled 10 Years of Partnering Contracts, suggests they have. For example, the national Job Centre Plus office programme was delivered under PPC by the Department for Work and Pensions and Land Securities Trillium for 拢737m, which was a 25% saving on the forecast price of 拢981m. And Hackney Homes鈥 housing refurbishment programme, which combined the component supply chain arrangements of five contractors, achieved a saving of up to 20%.
The key to these results lies in the opportunity that PPC gives to analyse price assumptions during the contractor鈥檚 early conditional appointment and to agree better deals before authorising work on site. This is done by programmed design review and supply chain re-engineering, which ensures the best use of the extra thinking time.
If there is no scope to achieve savings, clients at least need to stay within their budget. The ACA case studies include two PPC academy projects for the City of London, a schools programme for Harrow council, and a station refurbishment project for Virgin Trains that all met demanding targets. Behind this lies the contractual commitment to work within a stated budget and an agreement that if the budget is exceeded, the client can terminate all appointments ahead of starting on site.
But have savings been achieved at the expense of quality? The 拢22m Bermondsey Academy project, under which Willmott Dixon and other team members navigated the risks of site contamination and site relocation, was awarded the DTI/CE Quality in Construction Award and the Prime Minister鈥檚 Better Public 好色先生TV Award in 2006. So with clear contractual controls during preconstruction, it is possible to reconcile cost savings with good-quality design and construction.
The other big drivers in the current era are designs that reduce waste, carbon emissions and energy consumption, and construction that offers training and jobs. The formal two-stage PPC process allows the parties to interrogate subcontractors and suppliers on the cost and value of their sustainability proposals and apprenticeship schemes, so the client can decide whether they are affordable. Golding Homes, for example, worked with Vinci on a PPC housing improvement programme that allowed Mid Kent College and North Kent Construction Skills to create training schemes and apprenticeships for kitchen and bathroom works. Similarly, Whitefriars Housing, with Wates and Lovells, set up an agency under PPC that secured 200 training opportunities over a five-year 拢230m housing refurbishment programme.
But what if things go wrong under PPC? The key is to put in place communication systems within the 鈥渃ore group鈥, which is obliged to meet and look at any problem before it is taken to another level of dispute resolution. This approach was used with the refurbishment of Bewick Court in Newcastle, where constructor Kendal Cross overcame the insolvency of a key cladding specialist by taking on its employees and completing the cladding works itself, having secured client agreement through core group consultation. The alternative was a delay
and cost overrun that would have soured the job at an early stage and almost certainly resulted in disputes.
Another example of risk management was the 拢17m Manchester Piccadilly Ramada Hotel, where a complex refurbishment programme, and the need to keep the hotel operational, created a continually changing brief and significant risks on site. The core group had to ensure that work stopped, when necessary, on what project manager Jones Lang LaSalle described as 鈥渘ot a project for the faint-hearted鈥.
To date, no PPC project has been to litigation or arbitration, and only a handful have been to adjudication, despite throughput worth several billion pounds a year, according to the RICS. So, the partnering teams must be doing something right.
The 2008 Arup Report for OGC described PPC2000 as 鈥渁 complete procurement and delivery system that is distinct from other forms of contract鈥, and the case studies in the 10th anniversary publication suggest this contract is as relevant now as ever.
David Mosey is head of construction at Trowers & Hamlins, and was involved in drafting PPC2000.
Visit www.ppc2000.co.uk to download the ACA鈥檚 10 Years of Partnering Contracts
No comments yet