ºÃÉ«ÏÈÉúTV

Read our policy.

The indicative costs are based on a typical primary school located in Ealing, Middlesex with a gross internal floor area of 3,000m2. The building includes 14 classrooms, four group rooms, a conference room, gymnasium, music room, four miscellaneous rooms, four offices, one nursery room, two kitchens, a library, dining room, staff room, toilets and changing rooms.
ItemCost
Water supply 27.5m3 tank, single electric pump, underground pipework, pumproom pipework, valves and appurtenances (pump room and builders’ work by others)£50,000
Sprinkler heads 450@ £200 each (including pipework, bracketry and installation)£90,000
Sprinkler valve room£5,000
Documentation, operation and maintenance manuals£5,000
Total£150,000
Rule of thumb £30/m2 plus water supply