Local authorityOriginal expected project completion dateCurrent expected project completion dateMajor reasons for delay
BradfordDec-07Sep-08Challenging original completion expectations; Issues around use of untested processes
BristolApr-08Jan-09Challenging original completion expectations; Issues around use of untested processes
GreenwichApr-09Sep-11Piloting of non-standard BSF procurement model by local authority has been problematic and has caused considerable delay; Local resourcing difficulties; Issues around use of untested processes
KnowsleySep-09Jan-10Issues around use of untested processes
LeedsSep-10Sep-11Issues around use of untested processes
LewishamJul-10Sep-10Issues around use of untested processes
ManchesterSep-09Jun-11Challenging original completion expectations; Issues around use of untested processes; later project rescoping, including integrating seven new academies
NewhamJan-09Mar-11Challenging original completion expectations; Issues around use of untested processes; Local resourcing difficulties
SheffieldMar-10Apr-11Challenging original completion expectations; Issues around use of untested processes
SolihullSep-08Sep-09Challenging original completion expectations; Issues around use of untested processes
STaGDec-12Jan-13Issues around use of untested processes
SunderlandJan-10Sep-10Challenging original completion expectations; Issues around use of untested processes
Local authorityOriginal expected project completion dateCurrent expected project completion dateMajor reasons for delay
BirminghamSep-10Sep-11Challenging original completion expectations; Local resourcing difficulties; More time taken to develop transformational strategy; later project rescoping, including integrating new academies
HackneySep-13Nov-13Issues around use of untested processes
HaringeyMar-11Oct-11Issues around use of untested processes
IslingtonSep-11Sep-12Local resourcing difficulties; More time taken to develop transformational strategy
LiverpoolSep-10Sep-11Local resourcing difficulties; More time taken to develop transformational strategy; Issues around use of untested processes; Piloting of non-standard BSF procurement model by local authority has caused some delay
MiddlesbroughSep-11Sep-12Local resourcing difficulties; changes to procurement strategy to achieve a better value for money outcome caused some delay
Tower HamletsJun-11Dec-11Local resourcing difficulties; More time taken to develop transformational strategy
Local authorityOriginal expected project completion dateCurrent expected project completion dateMajor reasons for delay
LutonSep-10Nov-12Local resourcing difficulties; Issues around identifying new sites for new schools have caused delay to the project
N LincsJun-11Apr-12Local resourcing difficulties; More time taken to develop transformational strategy
SalfordJan-12Sep-12More time taken to develop transformational strategy
SandwellMar-11Jul-11More time taken to develop transformational strategy
TamesideJan-11Feb-11More time taken to develop transformational strategy