- ºÃÉ«ÏÈÉúTV
All the latest updates on building safety reformRegulations latest
- Focus
- Comment
- Programmes
- CPD
- ºÃÉ«ÏÈÉúTV the Future
- Data
2024 events calendar
ºÃÉ«ÏÈÉúTV Awards
Keep up to date
- ºÃÉ«ÏÈÉúTV Boardroom
All the latest updates on building safety reform
2024 events calendar
ºÃÉ«ÏÈÉúTV Awards
Keep up to dateLocal authority | Original expected project completion date | Current expected project completion date | Major reasons for delay |
Bradford | Dec-07 | Sep-08 | Challenging original completion expectations; Issues around use of untested processes |
Bristol | Apr-08 | Jan-09 | Challenging original completion expectations; Issues around use of untested processes |
Greenwich | Apr-09 | Sep-11 | Piloting of non-standard BSF procurement model by local authority has been problematic and has caused considerable delay; Local resourcing difficulties; Issues around use of untested processes |
Knowsley | Sep-09 | Jan-10 | Issues around use of untested processes |
Leeds | Sep-10 | Sep-11 | Issues around use of untested processes |
Lewisham | Jul-10 | Sep-10 | Issues around use of untested processes |
Manchester | Sep-09 | Jun-11 | Challenging original completion expectations; Issues around use of untested processes; later project rescoping, including integrating seven new academies |
Newham | Jan-09 | Mar-11 | Challenging original completion expectations; Issues around use of untested processes; Local resourcing difficulties |
Sheffield | Mar-10 | Apr-11 | Challenging original completion expectations; Issues around use of untested processes |
Solihull | Sep-08 | Sep-09 | Challenging original completion expectations; Issues around use of untested processes |
STaG | Dec-12 | Jan-13 | Issues around use of untested processes |
Sunderland | Jan-10 | Sep-10 | Challenging original completion expectations; Issues around use of untested processes |
Local authority | Original expected project completion date | Current expected project completion date | Major reasons for delay |
Birmingham | Sep-10 | Sep-11 | Challenging original completion expectations; Local resourcing difficulties; More time taken to develop transformational strategy; later project rescoping, including integrating new academies |
Hackney | Sep-13 | Nov-13 | Issues around use of untested processes |
Haringey | Mar-11 | Oct-11 | Issues around use of untested processes |
Islington | Sep-11 | Sep-12 | Local resourcing difficulties; More time taken to develop transformational strategy |
Liverpool | Sep-10 | Sep-11 | Local resourcing difficulties; More time taken to develop transformational strategy; Issues around use of untested processes; Piloting of non-standard BSF procurement model by local authority has caused some delay |
Middlesbrough | Sep-11 | Sep-12 | Local resourcing difficulties; changes to procurement strategy to achieve a better value for money outcome caused some delay |
Tower Hamlets | Jun-11 | Dec-11 | Local resourcing difficulties; More time taken to develop transformational strategy |
Local authority | Original expected project completion date | Current expected project completion date | Major reasons for delay |
Luton | Sep-10 | Nov-12 | Local resourcing difficulties; Issues around identifying new sites for new schools have caused delay to the project |
N Lincs | Jun-11 | Apr-12 | Local resourcing difficulties; More time taken to develop transformational strategy |
Salford | Jan-12 | Sep-12 | More time taken to develop transformational strategy |
Sandwell | Mar-11 | Jul-11 | More time taken to develop transformational strategy |
Tameside | Jan-11 | Feb-11 | More time taken to develop transformational strategy |
Site powered by