- ºÃÉ«ÏÈÉúTV
All the latest updates on building safety reformRegulations latest
- Focus
- Comment
- Programmes
- CPD
- ºÃÉ«ÏÈÉúTV the Future
- Data
2024 events calendar
ºÃÉ«ÏÈÉúTV Awards
Keep up to date
- ºÃÉ«ÏÈÉúTV Boardroom
All the latest updates on building safety reform
2024 events calendar
ºÃÉ«ÏÈÉúTV Awards
Keep up to datePrice changes | |
% change June 1999 to June 2000 | |
Disposal of excavated materials | +2 |
Hardcore | +2.5 |
Granular fill | +1.5 |
Engineering bricks | +5 |
Ready-mixed concrete | +4.5 |
Reinforcement | +2.5 |
Concrete blocks | +7 |
Precast concrete lintels | +3 |
Steel universal beams and columns | +6 |
Sawn softwood | +3 |
Concrete roof tiles | +5 |
Clay roof tiles | +5 |
Reconstructed slates | +5 |
Plasterboard | +5 |
Plywood linings | +2 |
Softwood windows | +10 |
Vinyl floor tiles | +5 |
Paints | +3 |
Sanitaryware | +3 |
Polystyrene insulation | +8 |
Macadam road surfacings | +3 |
Cast-iron gutters, pipes and fittings | +4 |
PVCu pipes and fittings | +4 |
Hot rates | ||||
Unit | South-east £ | East Anglia £ | South-west £ | |
Rainwater pipework | ||||
110 mm plastic pipe, including brackets | m | 15.5 | 13 | 12.8 |
Extra for access pipe | item | 15 | 12.5 | 12.4 |
100 mm powder-coated aluminum pipe, including brackets | m | 37 | 33.5 | 33 |
Extra for swan-neck projection | item | 46 | 41.5 | 41 |
100 mm cast-iron pipe, including holderbats | m | 35 | 32.5 | 31 |
Extra for bend | item | 39 | 34 | 33.5 |
Rainwater gutters | ||||
Powder-coated aluminium half-round gutter, 113 × 56 mm | m | 25 | 22.5 | 22 |
Extra for stop end | item | 5 | 4.5 | 4.5 |
Aluminium box gutter, 600 mm girth | m | 42 | 37.5 | 37 |
Foul drainage above ground | ||||
100 mm PVCu pipe, including brackets | m | 16.25 | 13.5 | 13.35 |
Extra for bend | item | 10 | 8.2 | 8.1 |
38-40 mm MPVCu pipe, including brackets | m | 6.35 | 5.25 | 5.2 |
Extra for bend | item | 3 | 2.5 | 2.45 |
PVCu bottle trap, 40 mm outlet | item | 5.95 | 4.9 | 4.85 |
Drainage below ground | ||||
Excavating trench for pipe not exceeding 200 mm diameter, backfill with selected excavated material – average depth 1750-2000 mm | m | 27.5 | 24.35 | 24 |
– average depth 2000-2250 mm | m | 33 | 29.35 | 29 |
Bed and surround in granular material for 100 mm pipe | m | 7.85 | 7 | 6.9 |
PVCu pipe, 100 mm diameter | m | 6.5 | 5.75 | 5.7 |
Clay pipe, 100 mm diameter | m | 7 | 6.25 | 6.15 |
Extra for bend | item | 10.35 | 9.15 | 9 |
Clay pipe, 150 mm diameter | m | 11.25 | 10 | 9.85 |
Extra for bend | no | 15.5 | 13.8 | 13.65 |
Cast-iron pipe, 100 mm diameter | m | 25 | 23 | 22.75 |
Manholes | ||||
Excavating 2 m maximum depth | m3 | 7.5 | 6.75 | 6.7 |
Engineering brick class B walls, one-brick thick, fairfaced one side | m2 | 73.5 | 65 | 64.5 |
Step iron | item | 5.3 | 4.75 | 4.7 |
Land drainage | ||||
Perforated clay pipe, 100 mm diameter | m | 5.5 | 5 | 5 |
Extra for bend | item | 10 | 9 | 8.8 |
Key indicators | |
% change June 1999 to June 2000 | |
Retail prices index | |
Headline rate | 3.3 |
All items, excluding mortgage interest payments – government’s target index | 2.2 |
All items, excluding mortgage interest payments and indirect taxes | 2 |
Industry generally | |
Materials and fuel purchased by manufacturing industry | 14 |
of which: materials | 16.1 |
of which: fuel | –1.8 |
Materials and fuel purchased by manufacturing, excluding food, beverages, petroleum and tobacco industries | 5 |
Output prices of manufactured products | 2.9 |
Output prices of manufactured products, excluding food, beverages, petroleum or tobacco | 1 |
Construction industry | |
Construction materials | 2.5 |
Housebuilding materials | 2.2 |
Machinery and equipment | 1.8 |
Electrical machinery and apparatus | –0.2 |
Source: Office for National Statistics. June 2000 figures are provisional. Machinery and equipment includes mechanical engineering items such as pumps, taps, valves, lifts, and cooling and ventilation equipment. Electrical machinery and apparatus includes electrical engineering materials such as electricity distribution and control apparatus, wires and cables and lighting equipment. |
Packages whose indices have risen most | ||
Work category | Index title | % rise July 1999-July 2000 |
3-22 | Cladding and covering: aluminium | 12.2 |
3-35 | Windows and doors: softwood | 10.6 |
3-27 | Waterproofing: liquid applied coatings | 10.1 |
3-24 | Cladding and covering: zinc | 9.7 |
3-50 | Insulation | 8.8 |
3-58 | Pipes and accessories: copper | 8.4 |
3-01 | Demolitions | 6.5 |
3-16 | Cladding and covering: fibre cement | 6.4 |
3-17 | Cladding and covering: coated steel | 6.2 |
3-51 | Pavings: coated macadam and asphalt | 6 |
CIJC wage agreement 2000-2002 | |||
26-Jun-00 | Basic pay (p/hour) 25 June 2001 | 24-Jun-02 | |
General operative | 478 | 504 | 549 |
Skill rate 4 | 515 | 543 | 591 |
Skill rate 3 | 546 | 576 | 627 |
Skill rate 2 | 583 | 615 | 670 |
Skill rate 1 | 605 | 638 | 695 |
Craft rate | 635 | 670 | 730 |
All-in hourly rates for craft and general operatives | |||||
Time (weeks) | Craft (£/week) | (£/²â±ð²¹°ù) | General (£/week) | (£/²â±ð²¹°ù) | |
Wages at standard basic rate, productive time | 47.8 | 247.65 | 11 837.67 | 186.42 | 8910.88 |
Lost time allowance (2%) | 0.9 | 247.65 | 223.88 | 186.42 | 168.52 |
Non-productive overtime | 1.74 | 247.65 | 430.91 | 186.42 | 324.37 |
Sub-total | 12 492.46 | 9403.77 | |||
Annual CITB allowance (0.5% of payroll) | 70.04 | 52.72 | |||
Annual and public holidays | 5.8 | 261.35 | 1515.82 | 196.73 | 1141.04 |
Employer’s contributions to retirement cover scheme | 52 | 1.9 | 98.8 | 1.9 | 98.8 |
National Insurance (average weekly payment) | 48 | 21.5 | 1032.18 | 13.65 | 655.35 |
Sub-total | 15 209.30 | 11 351.69 | |||
Severance pay and sundries (1.5%) | 228.14 | 170.28 | |||
Employer’s liability and third-party insurance (2%) | 308.75 | 230.44 | |||
Total cost/year | 15 746.19 | 11 752.41 | |||
Total cost/hour | 8.45 | 6.3 | |||
Calculation includes for five days sickness, in periods not exceeding three consecutive days, for which no payment is due. Holiday pay is based on the employer paying regular sums into the Template Holiday with Pay scheme sufficient to cover holiday pay in line with the Working Rule Agreement and the Working Time Regulations. All National Insurance payments are at not-contracted-out rates applicable from 6 April 2000. |
Wage agreement summary for major wage-fixing bodies | |||
Operatives | Agreement body | Wage rates effective since | Date of next review |
Builders and civil engineering operatives | Construction Industry Joint Council | 26-Jun-00 | A three-year agreement was promulgated in June 2000. The second part of the agreement comes into effect on 25 June 2001. |
ºÃÉ«ÏÈÉúTV & Allied Trades | 12-Jun-00 | 11-Jun-01 | |
Joint Industrial Council (BATJIC) | |||
Plumbers | The Joint Industry Board for Plumbing Mechanical Engineering Services in England and Wales | 21-Aug-00 | Aug-01 |
Scottish and Northern Ireland Joint Industry Board for the Plumbing Industry | Aug-00 | Aug-01 | |
Heating and ventilation operatives | Joint Conciliation Committee of the Heating, Ventilating and Domestic Engineering Industry | 23-Aug-99 | Existing agreement to expire on 4 September 2000. Negotiations still under way in mid-August |
Electricians | The Joint Industry Board for the Electrical Contracting Industry | ||
– main operatives | 07-Feb-00 | 8 January 2001 Rates will rise 12.3% in second part of two-stage | |
– apprentices | 04-Oct-99 | Oct-00 | |
Scottish Joint Industry Board for the Electrical Contracting Industry | 07-Feb-00 | 08-Jan-01 |
Site powered by