ºÃÉ«ÏÈÉúTV

Read our policy.

Elemental cost analysis (gross internal floor area 558 m2)
Main elementBreakdown££/³¾2%Specification
Demolitionsdemolitions24,483.1243.881.53%Site clearance and internal alterations
Substructurefoundations109,754.05196.696.87%Cast bored insitu piles
Superstructureframe59,213.55106.123.71%Insitu concrete frame
Ìýupper floors93,528.15167.615.85%Precast tiered floor
Ìýroofs127,043.11227.687.95%Standing seam aluminium on steel frame
Ìýstairs0.000.000.00%Ìý
Ìýexternal walls and cladding237,853.43426.2614.89%Curtain walling and rain screen cladding
Ìýwindows included in walls0.000.00%Velfac to temporary reception
Ìýexternal doors21,781.1339.031.36%Automatic revolving door to main entrance
Ìýinternal partitions51,108.8991.593.20%Blockwork/stud mix – internal glazed screens
Ìýinternal doors16,486.2429.551.03%Timber doorsets
Finisheswalls53,711.9696.263.36%Acoustic panelling to theatre
Ìýfloors64,054.04114.794.01%Hardwood strip to theatre
Ìýceilings38,361.6568.752.40%Acoustic suspended ceilings
Built-in fittingsfixed furniture only68,662.41123.054.30%Seating to theatre with writing tablets
Servicessanitary fittings 5,134.129.200.32%Ìý
Ìýservices infrastructure5,850.8310.490.37%Ìý
Ìýdisposal installations4,603.008.250.29%Ìý
Ìýmechanical services161,187.28288.8710.09%Low-energy displacement ventilation
Ìýelectrical services135,466.36242.778.48%Ìý
Ìýlift installation10,332.9018.520.65%Disabled access lifts
ÌýIT cabling17,841.7531.971.12%Cabling to theatre seats
Ìýbuilders work in connection21,418.1638.381.34%Ìý
External worksexternal finishes and planting80,039.15143.445.01%Cycle parking
Drainagedrainage 17,113.7430.671.07%Ìý
Ìýexternal services0.000.000.00%Ìý
PreliminariesÌý172,495.87309.1310.80%Ìý
Total cost Ìý1,597,524.872862.95100.00%Ìý
Cost per seat Ìý8,589ÌýÌýÌý