Analysis of the model |
Ìý | Element cost (£) | £/³¾2 gifa | % of total cost |
Substructure | 6 597 700 | 97.74 | 6.76 |
Foundations: bored piles 30 m deep and 1.5-2.4m diameter; 500 mm thick ground slab | Ìý | 4210 m2 @ | £370 |
Extra for two-level basement construction: diaphragm walls; insitu concrete frame and floors; waterproofing; drainage | Ìý | 8400 m2 @ | £600 |
Frame | 13 882 000 | 205.66 | 14.23 |
Insitu concrete shear wall construction to cores, average 250 mm thick | Ìý | 21 800 m2 @ | £115 |
Structural steel frame to upper floors and roof, allowance based on 90 kg/m2 | Ìý | 6000 t @ | £1,500 |
Additional secondary steelwork for trimming openings and so on | Ìý | 300 t @ | £1,800 |
Fire protection: mineral wool slab | Ìý | 87 750 m2 @ | £20 |
Concrete casing to perimeter columns at ground floor only | Ìý | item @ | £80 000 |
Upper floors | 3 461 000 | 51.27 | 3.55 |
Composite floor construction: 150 mm thick reinforced insitu concrete suspended slab; galvanised steel decking; total design load 5 kN/m2 | Ìý | 61 400 m2 @ | £55 |
Extra for 7.5 kN/m2 loading to 5% of floor area | Ìý | 3400 m2 @ | £10 |
Allowance for knocked panels in upper floor construction | Ìý | item @ | £50 000 |
Roof | 369 600 | 5.48 | 0.38 |
Composite roof slab construction: 150 mm thick reinforced insitu concrete; galvanised steel decking; PVC membrane; insulation; ballast | Ìý | 1920 m2 @ | £100 |
Extra for 7.5kN/m2 loading to plant areas: heavy-duty waterproofing membrane | Ìý | 1000 m2 @ | £20 |
Allowance for perimeter safety rails | Ìý | 176 m @ | £100 |
Allowance for plant bases and paved access routes to plant areas | Ìý | item @ | £20 000 |
Allowance for roof-level plant enclosures: structural steel frame; profiled aluminium raised-seam roof cladding; insulation | Ìý | item @ | £120 000 |
Stairs | 2 530 000 | 37.48 | 2.59 |
Precast concrete escape stairs rising 35 floors overall: balustrades; handrails; finishes | Ìý | 300 flights @ | £8,000 |
Precast concrete escape stairs rising two floors overall from basements: balustrades; handrails; finishes | Ìý | 16 flights @ | £5,000 |
Allowance for ladders and catwalks in plant rooms | Ìý | item @ | £50 000 |
External walls | 20 222 900 | 299.6 | 20.73 |
Aluminium-framed full-height curtain wall: double-glazed units; solar control glazing; toughened outer pane; laminated inner; opaque glazed spandrel panels | Ìý | 22 700 m2 @ | £800 |
Double-glazed Planar frameless glazing includnig secondary steel supports | Ìý | 1150 m2 @ | £600 |
Cladding to roof-level plant rooms: structural steel framing; composite panels; blockwork backing wall; louvres | Ìý | 500 m2 @ | £300 |
Louvres as external walling to plant room floors including louvre screen to open roof-level plant areas | Ìý | 1750 m2 @ | £400 |
Cladding to soffits, silver anodised aluminium | Ìý | 270 m2 @ | £270 |
Column casings, silver anodised aluminium | Ìý | 500 m2 @ | £300 |
Allowance for entrance canopy | Ìý | item @ | £100 000 |
Allowance for mock-ups, testing and so on | Ìý | item @ | £200 000 |
External doors | 175 000 | 2.59 | 0.18 |
Double-glazed aluminium frame exit and fire escape doors | Ìý | item @ | £50 000 |
Motorised revolving doors: 2.5 m diameter; glass/stainless steel enclosure | Ìý | 2 @ | £35 000 |
Access doors to roof plant areas | Ìý | item @ | £15 000 |
Motorised security shutters to car park/loading bay entrance | Ìý | item @ | £40 000 |
Internal walls and partitions | 3 006 800 | 44.55 | 3.08 |
Metal stud walls to lift shafts and services risers, two-hour fire resistance | Ìý | 18 300 m2 @ | £90 |
Metal stud partitions, one-hour fire resistance | Ìý | 10 550 m2 @ | £45 |
Allowance for partitions to basement, plant and storage areas | Ìý | 2000 m2 @ | £40 |
Blockwork backing walls to stone cladding in lobby areas | Ìý | 1000 m2 @ | £40 |
WC cubicles, including doors and ironmongery | Ìý | 370 @ | £1,500 |
Full-height laminate-faced duct access panels to WCs | Ìý | 1750 m2 @ | £120 |
Internal doors | 2 070 000 | 30.67 | 2.12 |
Single doors and frames to office areas: fire-rated hardwood veneered doorsets; vision panels; stainless steel ironmongery | Ìý | 400 @ | £1,700 |
Double doors and frames to office areas: fire-rated hardwood veneered doorsets; vision panels; stainless steel ironmongery | Ìý | 260 @ | £2,000 |
Double doors to riser cupboards:fire-rated full-heighted hardwood veneered doors; solid hardwood frame; ironmongery | Ìý | 420 @ | £1,500 |
Doors and frames to plant room areas: steel doorsets; fire-rated where required; stainless stell ironmongery | Ìý | 420 @ | £1,000 |
Allowance for fire-rated access panels | Ìý | item @ | £200 000 |
Wall finishes | 73 400 | 58.72 | 3.79 |
Stone cladding to entrance lobby walls | Ìý | 100 m2 @ | £300 |
Plasterboard drylining to concrete shear walls in cores, emulsion paint finish | Ìý | 11 200 m2 @ | £40 |
Self-coloured render finish to lift lobby walls on upper floors | Ìý | 5800m2 @ | £120 |
Drylining to perimeter columns in office areas | Ìý | 7800 m2 @ | £45 |
Glass-reinforced gypsum column casings to office areas | Ìý | 500 m2 @ | £300 |
Emulsion paint to circulation areas, plant rooms and so on | Ìý | 9800 m2 @ | £5 |
Ceramic tiling to toilets and cleaners' cupboards | Ìý | 2900 m2 @ | £65 |
Floor finishes | 97 150 | 77.72 | 5.01 |
Granite tile to lobby areas: lightweight concrete to make-up levels; screed; skirtings | Ìý | 750 m2 @ | £170 |
Unvitrified ceramic tiles to WCs: lightweight concrete to make-up levels; screed; skirtings | Ìý | 2230 m2 @ | £90 |
Carpet to lift lobbies and circulation areas: lightweight concrete to make-up levels; screed; skirtings | Ìý | 4110m2 @ | £80 |
Floor finish to plant and ancillary areas: coloured epoxy resin; screed | Ìý | 3900 m2 | £25 |
Floor finish to loading dock, parking and ramps | Ìý | 1900 m2 | £10 |
Allowance for matwells | Ìý | item @ | £20 000 |
Ceiling finishes | 459 200 | 6.8 | 0.47 |
Glass-reinforced gypsum feature ceiling to entrance lobby | Ìý | 750 m2 | £200 |
Concealed grid plasterboard suspended ceilingto lift lobbies and circulation areas and bulkheads | Ìý | 3400 m2 @ | £45 |
Concealed grid metail tray suspended ceiling to WCs | Ìý | 2230 m2@ | £40 |
Paint finish to sofitt of slabs to plant rooms, ancillary spaces and car parking | Ìý | 5800 m2 | £5 |
Acoustic installation lining to car park soffit | Ìý | 1900 m2 | £20 |
Furniture and fittings | 1 075 000 | 15.93 | 1.1 |
Allowance for water feature to main entrance lobby | Ìý | item @ | £75 000 |
Granite vanity tops | Ìý | 500 m2 | £750 |
Allowance for fittings to WCs | Ìý | item @ | £400 000 |
Reception desk | Ìý | item @ | £45 000 |
Main entrance and statutory signage | Ìý | item @ | £100 000 |
Car park bollards, column guards, entrance barrier | Ìý | item @ | £50 000 |
Rubbish compactor | Ìý | item @ | £30 000 |
Sanitary fittings | 324 000 | 4.8 | 0.33 |
Allowance for sanitary fittings | Ìý | 1200 m2 @ | £270 |
Water installations | 911 300 | 13.5 | 0.94 |
Hot and cold water: boosted copper rising main; bulk storage; boosted cold water distribution; localised electric heating | Ìý | 67 500 m2 @ | £13.50 |
Space heating and air treatment | 8 707 500 | 129 | 8.93 |
Gas installation | Ìý | item @ | £40 000 |
Low-temperature hot-water heating: perimeter heating installation to offices; emitters; pipework; insulation; gas-fired boilers | Ìý | 67 500 m2 @ | £45 |
Air-conditioning installation: air-handling plant; refrigeration; chilled water distribution for four-pipe fan coil installation to offices; ductwork terminated at cores | Ìý | 67 500 m2 @ | £75 |
Toilet extract installation | Ìý | 67 500 m2 @ | £4 |
Smoke extract installation | Ìý | 67 500 m2 @ | £3 |
Car park and loading dock extract ventilation | Ìý | 1900 m2 @ | £50 |
Electrical installations | 2 545 000 | 37.7 | 2.61 |
Mains and sub-mains installation | Ìý | item @ | £500 000 |
Power supply to mechanical plant | Ìý | 67 500 m2 @ | £4 |
Low-voltage distribution in risers to office areas | Ìý | 44 300 m2 @ | £10 |
Lighting, emergency lighting and small power to landlord's areas | Ìý | 20 200 m2 @ | £45 |
Lighting and emergency lighting to car park and loading bay | Ìý | 1900 m2 @ | £20 |
Allowance for enhanced lighting to reception and lobbies | Ìý | item @ | £75 000 |
Allowance for external lighting | Ìý | item @ | £150 000 |
Allowance for beacon and aircraft safety lights | Ìý | item @ | £10 000 |
Stanby power installation; life safety systems only | Ìý | item @ | £150 000 |
Lift installations | 5 200 000 | 77.04 | 5.33 |
21-person, 1600 kg lift serving 18 floors, 3 m/sec | Ìý | 6 @ | £200 000 |
21-person, 1600 kg lift serving 35 floors, 6 m/sec | Ìý | 10 @ | £280 000 |
10-person, 800 kg firefighters' lift serving 35 floors | Ìý | 4 @ | £200 000 |
Goods lift: 3000 kg serving 35 floors | Ìý | 2 @ | £200 000 |
Protective installations | 1 474 500 | 21.84 | 1.51 |
Sprinklers: single level to all areas; common bulk storage; split landlord/tenant pumpsets | Ìý | 67 500 m2 @ | £19 |
Dry riser installation | Ìý | item @ | £50 000 |
Hose reels including booster set | Ìý | 140 @ | £800 |
Lighting protection | Ìý | item @ | £30 000 |
Communication installations | 960 000 | 14.22 | 0.99 |
Fire-detection, voice alarm and public address system: analogue addressable with interfaces to mechanical plant, lift controls, sprinkler installation and building management system | Ìý | 67 500 m2 @ | £9 |
Primary vertical containment and distribution for data and communications systems | Ìý | 67 500 m2 @ | £3 |
Security installation: closed-circuit television and intruder detection | Ìý | item @ | £150 000 |
Special installations | 1 525 000 | 22.59 | 1.56 |
ºÃÉ«ÏÈÉúTV management system with lighting control | Ìý | 67 500 m2 @ | £18 |
Fully automated facade cleaning cradle | Ìý | item @ | £250 000 |
Communications mast | Ìý | item @ | £60 000 |
Builders work in connection | 1 086 000 | 16.09 | 1.11 |
Associated builder's work: services ducts and risers; holes; sleeves; chases; bases; firestopping, and so on, allow 5% | Ìý | item @ | £1 086 000 |
Preliminaries and contingencies | 17 592 200 | 260.63 | 18.03 |
Construction manager's fee, site supervision, multi-service gangs, site establishment and trade contractor's preliminaries, allow 17% | Ìý | item @ | £13 594 000 |
Design and contingency allowance, allow 5% | Ìý | item @ | £3 998 200 |
Total for shell-and-core construction | 97 557 000 | 1445.29 | 100 |
Ìý | Element cost (£) | £/³¾2 gifa | % of total cost |
Category A fit-out | Ìý | Ìý | Ìý |
Wall finishes | 243 600 | 3.61 | n/a |
Vinyl wallpaper to drylining in office areas | Ìý | 20 300 m2 @ | £12 |
Floor finishes | 2 879 500 | 42.66 | n/a |
Medium-grade access floor, dust sealant | Ìý | 44 300 m2 @ | £35 |
Carpet tiles | Ìý | 44 300 m2 @ | £30 |
Ceiling finishes | 2 436 500 | 36.1 | n/a |
Concealed grid metal tray suspended ceiling to office areas: acoustic quilt; fire breaks | Ìý | 44 300 m2 @ | £55 |
Fittings | 264 000 | 3.91 | n/a |
Manually operated blinds to office areas | Ìý | 8800 m2 @ | £30 |
Space heating and air treatment | 4 651 50 | 68.91 | n/a |
Extension of four-pipe fan coil installation into office areas: distribution ductwork; fan coil units; grilles and diffusers; insulation; condensate drainage; interface with building management system | Ìý | 44 300 m2 @ | £105 |
Electrical installations | 3 012 400 | 44.63 | n/a |
Small power to office areas: under floor distribution with one outlet per 5 m2 | Ìý | 44 300 m2 @ | £25 |
Lighting and emergency lighting to office areas | Ìý | 44 300 m2 @ | £43 |
Communications installations | 354 400 | 5.25 | n/a |
Final connections to fire, smoke-detection, alarm and public address systems in office areas | Ìý | 44 300 m2 @ | £8 |
Protective installations | 708 800 | 10.5 | n/a |
Single-leve sprinklers to office areas with one head per 9 m2 | Ìý | 44 300 m2 @ | £16 |
Special installations | 310 100 | 4.59 | n/a |
Extension of building management system into office areas | Ìý | 44 300 m2 @ | £7 |
Builders' work in connection | 452 000 | 6.7 | n/a |
Associated builder's work: holes; sleeves; chases; bases; firestopping and so on, allow 5% | Ìý | item @ | £452 000 |
Preliminaries and contingencies | 3 369 200 | 49.91 | n/a |
Contruction manager's fee, site supervision, multi-service gang, site establishment and trade contractor;s prelminaries, allow 17% | Ìý | item @ | £2 603 400 |
Design reserve and contingency allowances, allow 5% | Ìý | item @ | £765 800 |
Total for category A fit-out | 18 682 000 | 276.77 | n/a |
TOTAL CONSTRUCTION COST | 116 239 000 | 1722.06 | n/a |