Cost breakdown: Sobell House hospice
Item£
Preliminaries and fees436,386
Substructures173,696
Frame157,959
Upper floors30,000
Roof217,551
Stairs7,945
External walls101,795
Windows and external doors91,239
Internal walls and partitions84,415
Internal doors106,092
Wall finishes33,200
Floor finishes71,779
Ceiling finishes66,220
Fittings and furniture133,981
Sanitary appliances51,220
Disposal installations21,450
Mechanical installations 316,748
Electrical installations 360,522
Builders’ work in connection38,477
Site works255,985
Drainage49,288
External services15,586
Refurbishment of existing building218,642
Total3,040,176