Influential committee slams Network Rail鈥檚 overspend on its CP5 programme and says its regulator needs reviewing
The influential Public Accounts Committee has called for a 鈥渇undamental review鈥 of regulator the Office for Rail and Road after slamming Network Rail on overspend and delays during its Control Period 5 development programme.
In a report published this morning, MPs on the committee said the Office for Rail and Road (ORR) 鈥渓acks the capability to robustly scrutinise Network Rail鈥檚 plans and cost estimates鈥, and recommended the Department for Transport (DfT) launch a 鈥渇undamental review of the regulator鈥檚 role and effectiveness in rail infrastructure planning.鈥
The report said the DfT, Network Rail and the ORR had agreed an 鈥渦nrealistic鈥 programme of investment for CP5, which contained 鈥渢oo much uncertainty around the costs of large projects鈥 when it was signed off.
It also highlighted the 鈥渟taggering and unacceptable鈥 cost increase on the Great Western Main Line electrification project 鈥 which Network Rail鈥檚 chief executive Mark Carne (pictured) admitted has risen from 拢1.6bn to 拢2.8bn.
The report calls on the DfT and Network Rail to publish 鈥渁 full account of what has caused the cost increases to date and proposals for controlling future costs鈥.
A Network Rail spokesperson said: 鈥淚t is clear that we, as an industry, were overly ambitious about what could be accomplished with the funds and resources available to deliver the high levels of investment which will enable our railway to continue to cater for growing numbers of passengers and support economic growth.
鈥淣etwork Rail has successfully delivered over 5,000 projects over the past five years, but our understanding of how best to plan and deliver major new electrification schemes was not good enough. We have now made significant changes to the way we plan and deliver our investment programme, which will see schemes progress only once they are sufficiently developed that a reliable cost estimate can be established.
鈥淪ir Peter Hendy鈥檚 report on the deliverability of the current investment plan will be published later this month.鈥
An ORR spokesperson said: 鈥淲ith the changes to Network Rail鈥檚 ownership and finances since it became a public sector company, ORR agrees that a review of its own role in major projects is appropriate.
鈥淥RR looks forward to participating in this work to ensure that Network Rail鈥檚 extensive rail investment programme is delivered on behalf of taxpayers and users of the network.鈥
A DfT spokesperson said: 鈥淲e are proud to have a hugely ambitious investment programme, but agree that lessons should be learned on all sides. We are committed to seeing the 拢38 billion programme through and delivering the railway passengers deserve.
鈥淭hat鈥檚 why the Secretary of State asked Dame Colette Bowe to look at the lessons learned and make recommendations on what can be done better in future, and why Sir Peter Hendy is developing proposals to get the rail upgrade programme back on track and ensure it is both affordable and deliverable. Both reports will be published later in the autumn. We will respond to the PAC in due course.鈥
Public Accounts Committee recommendations:
- For the next planning round for rail investment, and in all future investment planning, the Government must assure itself that its plans can be delivered.
- For all rail spending decisions the Department for Transport (DfT), Network Rail and the Office of Rail and Road (ORR) must assess and explain how uncertainty in key projects could affect the plan鈥檚 overall costs and schedule.
- The DfT should carry out a fundamental review of the regulator鈥檚 role and effectiveness in rail infrastructure planning.
- The DfT, Network Rail and the ORR should put in place sharper accountability arrangements for major enhancement projects, such as the Great Western Main Line electrification. They should also agree principles on when it is appropriate to fund and manage these projects outside the five year rail funding cycle, and build in strong accountability mechanisms to avoid costly overruns.
- The DfT and Network Rail should publish an updated schedule and cost forecast for the Great Western Main Line electrification programme, a full account of what has caused the cost increases to date and proposals for controlling future costs, including the liabilities associated with the new electric trains.
- The DfT and Network Rail should publish a rail skills strategy for the industry with milestones for delivery.
- The DfT and Network Rail, drawing on the Hendy review, should publish a revised programme of rail electrification improvements, including the rationale for prioritisation between projects, with updated cost and delivery forecasts.
- The DfT and Network Rail need to have a clear and agreed public strategy about which rail projects are deliverable. Deadlines for key milestones must be clear, realistic, and transparent to passengers and the public.
No comments yet