Aecom has been drafted in to inspect Amey鈥檚 work

Oxgangs Primary School - Edinburgh

The PFI consortium responsible for structural defects across a spate of Edinburgh schools has agreed to sweeping concessions in a settlement with the local authority.

Edinburgh Schools Partnership (ESP) operated 17 schools which were forced to close in 2016 following the discovery of defects after a wall at one of them, Oxgangs Primary School, dramatically collapsed (pictured).

When the schools were built ESP was formed of Miller Construction, bought by Galliford Try in 2014, and Amey, who later pulled out of the consortium. 

ESP built 13 of the closed schools, with the remaining four built exclusively by Miller.

A settlement report published by client Edinburgh council does not include monetary details but alludes to cash compensation, work by ESP that will go unpaid, as well as further contractual requirements.

Part of the agreement sees a third-party, Aecom, drafted in to inspect the work on ESP鈥檚 FM sub-contractor Amey.

The settlement states: 鈥淭his new regime includes quarterly checks on Amey鈥檚 monitoring of, and compliance with, the contract, coupled with random or targeted sampling of the works and services undertaken by Amey. This will all be at ESP鈥檚 expense.鈥

A report by architect John Cole, published last year, found that 鈥減oor quality construction鈥 was responsible for the collapse of the Oxgangs Primary School walls. 

Settlement terms

  • All rectification work has been carried out at the sole expense of ESP or their sub-contractors. The report adds: 鈥淚t is understood that the cost of this is very significant鈥.
  • The council can retain an agreed sum with respect to structural building defects and fire-related works
  • The council and ESP agree to split the catering bill for the school closures period
  • ESP will agree to open the 17 school buildings for longer at no extra cost to the council (Approximately an extra 8-9 hours a week; to be used for sports and other activites)
  • Further contractual agreements have been placed on Amey to report performance or service failures
  • An additional independent inspection regime, led by Aecom, will report jointly to ESP and the council. ESP will pay for it