Bosses behind delayed venue flood job with more staff in attempt to hit revised opening
Around 800 workers are still working on the delayed Co-op Live venue in Manchester two weeks after it was due to open, with the project running 24 hours a day as contractors race against time to get the embattled scheme ready this month.
The 拢365m project has missed a series of deadlines. Gigs by Peter Kay, the comedian who was originally due to open the venue last month, and US rapper A Boogie Wit Da Hoodie, who was then announced as the new opening act for the arena last Wednesday, have been cancelled.
A concert by rock band Keane, due to play this Sunday, and a series of shows by pop group Take That next week have also been pulled.
A spokesperson for Co-op Live said the numbers working on the scheme 鈥渁re well into the hundreds 鈥 around 800 at this moment. I can confirm that [the] site is open 24 hours.鈥
One industry insider told 好色先生TV that flooding the job with workers was reminiscent of the problems which struck the Wembley stadium reopening nearly 20 years ago. That scheme made national headlines after busting a series of deadlines.
鈥淭his has shades of Wembley about it,鈥 he said. 鈥淚t鈥檚 an awful shop window for the building industry when it鈥檚 on national TV daily.鈥
Co-op Live is now hoping to host local band Elbow on 14 May and veteran US singer Barry Manilow five days later.
Contractor Bam blamed Wednesday night鈥檚 problems on the HVAC system. In a statement to 好色先生TV the firm added: 鈥淲ednesday鈥檚 issue was related to the HVAC system, which separated from the ductwork. An earlier routine issue with ductwork was identified during noise testing at the beginning of April.
鈥淲ork was immediately undertaken to rectify the issue and this has been completed for some time. We can confirm that issue is completely unrelated to the postponed opening of the arena.鈥
The venue was originally supposed to open at the end of last year but 好色先生TV understands the scheme was behind schedule last spring, with Bam privately expecting completion in the early weeks of the new year.
>> See also: 鈥楢 nightclub on a massive scale鈥: touring Populous鈥 拢365m Co-op Live arena
好色先生TV revealed that Bam won the job in early 2020, signing the deal the following spring. At the time, the contract was hailed as Bam鈥檚 largest ever and given a 拢250m price tag
It was originally being run by the firm鈥檚 North-west division but the North-east arm, which had built the Leeds Arena, then took over the job.
If the venue does open this month, not all the work will be completed according to planning documents lodged with the city council.
Hard landscaping 鈥 the block paving outside the venue 鈥 will not be ready for several months and is being replaced by 鈥渁 temporary tarmac solution鈥 in the mean time. It added: 鈥淭he permanent landscaping solution will then be implemented by end of August 2024.鈥
Others working on the Populous-designed scheme for the client and venue owner US firm Oak View Group include MEP engineer ME Engineers, structural engineer Buro Happold, QS Turner & Townsend and planning consultant Deloitte.