The government claims that flood protection spending is rising, but as the UK towels itself off after yet another deluge, the public is understandably sceptical. So what鈥檚 the real story?

floods

As the floods swept across large swaths of the UK over Christmas, the government recognised a potential PR disaster when it saw one. Within hours of the first homes being breached, members of the government from the prime minister down were out on the streets, doling out commiserations and trying to look like they could offer practical assistance.

Sure enough, the days that followed saw multiple stories appearing in local newspapers, on the television and radio, describing cuts to flood defence works. Without such cuts, the stories proclaimed, disaster could have been averted. But while there is little doubt that cases of pulled funding do exist, the national picture is far more complicated. So what is the truth about capital spending on flood defence works, now and in the future? And what challenges does the government face in ensuring that projects proceed as smoothly and effectively as possible?

Rising or falling?

In the aftermath of the worst of the floods, Defra minister George Eustice appeared on Radio 4鈥檚 Today programme. During a relatively good-natured exchange, he claimed that 鈥渨hen budgets across government are having to be cut, we have maintained spending on flood defence specifically鈥. He added: 鈥淲e are going to spend 拢2.3bn between 2015 and 2021, which will be an increase in real terms鈥 and 鈥渢he current spending period goes up to 2015 [and] in that period we鈥檝e spent about 拢2.3bn鈥.

Similar figures were repeated in an official statement from the department issued to 好色先生TV. However, it takes a bit of untangling to understand why the same amount of money spent first over four years and then over six is an increase 鈥渋n real terms鈥.

To take matters chronologically, between 2007/08 and 2010/11, the last government spent a total of 拢2.236bn on flood defence works. The equivalent allocation for the current spending period is 拢2.134bn, which amounts to an overall cut of 4.6%.

So the bare figures would seem to indicate that Eustice was being somewhat economical with the truth on Today. However, according to Defra his sums simply reflect the way in which flood defence spending has changed since the coalition took power. Under the new system, Defra delivery body the Environment Agency (EA) no longer pays the full cost of flood defence works, but instead seeks to attract partner funding from other public and private sector bodies. A Defra spokesperson said that these funds explain the gap between the 拢2.3bn claimed by Eustice and the official 拢2.134bn EA allocation - although he declined an invitation to provide further detail.

flood protection spending

But what about the assertion that 拢2.3bn over six years is an increase on 拢2.3bn over four years? This is explained by the fact that the figure for the six years from 2015 refers only to capital spending where previous figures quoted include both capital and revenue spending. Last year, Defra struck a deal with the Association of British Insurers (ABI) whereby in exchange for additional flood defence works, the ABI agreed to cap insurance premiums for homes in areas at risk of flooding (albeit, as the Financial Times revealed last week, around 9,000 homes weren鈥檛 included in the agreement). Under the agreement, the government agreed to increase capital spending on flood defence works to 拢370m a year for the next six years, compared with an average of 拢298m in the current spending period, which with a guarantee that the figure wouldn鈥檛 be eroded by inflation just about gets us to the 拢2.3bn over six years that Eustice mentioned.

This does beg the question, why didn鈥檛 he include the revenue spending? 鈥淭he revenue budget hasn鈥檛 been set,鈥 the Defra spokesperson told 好色先生TV. That鈥檚 no doubt true, but it may be that a recent Environment, Food and Rural Affairs select committee report criticising the depths of staff cuts at the EA was also a factor.

An uncertain future

To be fair to the government, no matter how much it commits to flood defence works, it will never be enough to protect every home in the land and to prevent the negative headlines that appeared over Christmas.
According to David Balmforth, senior vice president at the Institution of Civil Engineers: 鈥淚t will be almost impossible to get an objective view of what is a sensible amount of investment because it鈥檚 not a stationary problem. The world is moving both in how we live in the world and also in terms of climate change. And because we don鈥檛 have a crystal ball we can鈥檛 quantify that future. What I can say is that it isn鈥檛 possible or sensible for us to try to protect every single property in every single location for every single eventuality, and it will not be possible in the future.鈥

That said, there are clearly challenges facing the EA鈥檚 current and future programme of works. First of all, the delivery timetable has slipped. Last summer, the EA set a new framework for research and delivery partners - the Water and Environment Management (WEM) framework - following delays caused by problems identified in the procurement process. While hardly disastrous - had the framework been set up on time it would have done nothing to help those households affected over Christmas - the delay was nevertheless unhelpful.

There have been a couple of schemes where they were ready to go and there鈥檚 been an issue with one of the funders and things haven鈥檛 progressed

鈥淭here was a delay in the process for getting everyone on board, but they got it sorted out by the middle of last year,鈥 says Peter Phipps, head of geomorphology and coastal management at Mott MacDonald, one of the consultants that bid successfully for inclusion on the WEM framework. The company is currently working on a major flood wall project in Clacton, Essex, as well as a comprehensive review of Hartlepool鈥檚 sea defences. 鈥淚 think that generally the release of the projects has been slightly slower than the EA and the suppliers had hoped for,鈥 Phipps adds. 鈥淏ut it seems to be sorting itself out as we move forwards through that framework.鈥

The move towards the EA acting as just one of a group of investors also presents challenges. Put simply, the agency isn鈥檛 used to working in such a co-operative manner and needs time to adapt to the fact that there may be conflicts between the best technical solution for a scheme and the demands placed upon it by other funding partners, whether that be from a regeneration, economic development or heritage perspective, to name just three possibilities.

Then there is the added complexity that multiple partners bring to the basic financial management of a project. Different funding bodies and private companies operate on different financial cycles, so the challenge is to ensure that the money is available for delivery at the appropriate point in a project鈥檚 progression. What happens if one of the partners pulls out or simply doesn鈥檛 have the funds available at the right time? 鈥淭here have been a couple of schemes where they were ready to go and there鈥檚 been an issue with one of the funders and things haven鈥檛 progressed,鈥 says Phipps. 鈥淪o there is that issue around the partnership funding approach.鈥

Finally, there is the challenge of simply attracting more public and private funding into the EA鈥檚 flood defence pot, with the relatively small amount of alternative funding in the current spending period suggesting that things haven鈥檛 got off to a great start. Indeed, asked to name a project on which private capital had been successfully secured, one WEM framework member who preferred not to be named could only come up with one example, and that was still at the planning stage with no funds formally committed as yet. A Defra spokesperson said that 鈥渋t is still early days鈥.

However, according to industry experts we shouldn鈥檛 expect too much to happen too quickly. 鈥淭his is a journey,鈥 says Steve Thompsett, director of water and energy environment at Capita, another WEM framework member. 鈥淭he policy initiatives that kick these things off can take years to embed, so making this work and getting contributions is a challenging thing. It鈥檚 also not something that flood risk professionals and the EA have had to do for very long. It鈥檚 very much a learning curve. But if you want to deliver more, the money has to come from somewhere.鈥

Who鈥檚 doing what?

The companies and consortiums on the Water and Environment Management framework include:

Modelling, mapping and data Capita, Halcrow, Jackson-Hyder joint venture, Jacobs, Jeremy Benn Associates, Mott MacDonald

Environmental services Aecom Kier joint venture, Capita, Halcrow

Engineering and related services Capita, Halcrow, Jackson-Hyder joint venture, Jacobs, Mott MacDonald

Asset delivery BMM (Bam Nuttall, Mott MacDonald), GBV (Galliford Try, Black & Veatch), Jackson-Hyder JV, JN Bentley, Jeremy Benn Associates, Team Van Oord (Van Oord, JT Mackley, May Gurney, Royal HaskoningDHV), VBA (VolkerStevin, Boskalis Westminster, Atkins)

 