As Crossrail鈥檚 opening date is pushed further and further into the future and costs spiral over budget, Joey Gardiner asks why the biggest construction project in Europe has swerved so far off track and how this could impact the rest of the industry

shutterstock_586032545

鈥極n time and on budget.鈥 The number of times those following the construction of the UK鈥檚 most ambitious piece of new railway in a generation, Crossrail, listened to that monotonous mantra is probably beyond count. Throughout all evidence to the contrary, from strikes and design problems to a substation explosion and major contractor collapse, the same fixed mask was maintained to the outside world. 鈥淥n time. On budget.鈥

Except, as the world now knows, it鈥檚 not.

In July, transport minister Jo Johnson admitted the 拢14.8bn cross-London railway 鈥 Europe鈥檚 largest infrastructure project 鈥 was 拢590m over budget, citing 鈥渃ost pressures鈥. Then last week, the public company building it, Crossrail Ltd, admitted the central section will not open as planned in time for Christmas this year, but instead anything up to a year later. And even now the final cost of this latest delay is still to be quantified 鈥 with reports of a further 拢400m bill and no official pretence that even the budget announced in July can now be held. 

鈥淭his would and should have been brought in on time and on budget鈥

Rob Holden, ex-chief executive, Crossrail

With one national newspaper describing it as a 鈥渘ational embarrassment鈥 reminiscent of the construction of the Channel Tunnel, a senior contracting industry source said: 鈥淭he problem is we鈥檝e spent the last few years saying Crossrail was different, an exemplar of the industry working properly. This is not where we鈥檇 want to be.鈥

These problems follow a clean bill of health from the National Audit Office in 2014 and years of plaudits for the project. So, what has gone wrong at the UK鈥檚 flagship rail scheme, how much could it cost, and what might this all mean for the industry?

Desperate

The clear story that emerges from the various official and unofficial accounts is of multiple problems conspiring to make delay unavoidable. Despite desperate attempts to repair numerous cracks in the edifice, on 31 August the dam burst, with the official admission of delay until 鈥渁utumn鈥 next year. Being quizzed by the London Assembly last week, Crossrail chair Terry Morgan admitted his disappointment. 鈥淣umerous technical problems arose. As we mitigated one risk, other risks began to materialise,鈥 he said.

While construction issues have undoubtedly contributed, the immediate reason for the delay has been the failure of Crossrail to make progress installing and testing the immensely complex signalling software for the new railway, which has to do the job of linking the new underground signalling between London Paddington and Abbey Wood with the separate systems for the eastern and western overground sections. 

The difficulties of achieving this were clearly hugely exacerbated by the explosion of a premanufactured electricity substation at Pudding Mill Lane near Stratford last year, which Crossrail chief executive Simon Wright told the London Assembly had delayed the commencement of train testing from October last year to February this year. 

Political decisions

But many feel the problems go further back. Rob Holden was chief executive of the project until 2011, and blames the problems on the decision made shortly after his departure to delay procurement of the rolling stock. This was done amid political controversy over the award of a separate contract, for Thameslink rolling stock, to German firm Siemens, which was said to have jeopardised the future of the UK鈥檚 last train-making factory, based in Derby. Holden says this has meant the new rolling stock, which has to be totally integrated into the signalling system, is being brought in at the exact same time as the railway itself. 

He says: 鈥淭he one overriding lesson from the problems with the Channel Tunnel was to never ever bring in new trains and infrastructure at the same time. The original plan [for Crossrail] was the trains would be brought in earlier and tested on GWR lines to iron out issues beforehand 鈥 but the decision was taken to defer for political reasons.鈥

The upshot, Holden says, is that 鈥渂lame comes on the project, when actually this vital decision was taken in another place. This would and should have been brought in on time and on budget.鈥

鈥楽hort memory鈥

However, Crossrail鈥檚 Morgan denied the procurement delay had any relation to the project delay, accusing Holden of having 鈥渁 short memory鈥, and saying Transport for London welcomed the decision to change procurement route 鈥 from PFI to direct purchase 鈥 when it happened. 

A TfL spokesperson said: 鈥淭he procurement of the trains has had no impact on the delayed opening of the central section. Informed by the lengthy delays to the train procurement for the Thameslink project, which was carried out through a PFI, a decision was taken by the DfT and TfL that TfL would procure the trains directly. The risk to train delivery under a PFI was much greater. The only change we made to the train procurement was done with the clear intent of de-risking the programme. The trains are now being delivered, and are already serving parts of the Elizabeth line route in the east and the west.鈥

Either way, Holden says the delay demonstrates a failure in control of the project. 鈥淭he signalling system has always been the issue on the top of the risk register for this project, particularly given its complexity. It clearly has not been given the attention it deserves.鈥 

Crossrail鈥檚 Wright denied this to the Assembly. 鈥淚t鈥檚 an unprecedented scheme, combining three different systems. We always knew it was going to be hard, and it鈥檚 proven to be just that,鈥 he said, describing the signalling software as 鈥渋mmature鈥. 

鈥淭o bring together the systems together has been harder than we hoped. We started testing later than we wanted, and those tests have not gone as well as we鈥檇 hoped,鈥 he said.

Construction failures

Amid all this debate about the signalling, it might be tempting to believe that the construction industry has clean hands. Alas, this is very far from the truth. In fact, Crossrail鈥檚 statement announcing the delay made clear that part of the reason the testing programme has been compressed is because construction work has overrun. 

Wright told the Assembly that fit-out work in the tunnels is actually still ongoing, meaning that the tracks can only be accessed for testing part of the time, limiting the organisation鈥檚 options when problems arise. He said he didn鈥檛 anticipate starting 鈥24/7 testing鈥 until October. 鈥淭esting has been less than productive due to incomplete infrastructure, with assets not completed due to construction delays,鈥 he said.

While Wright did not detail the reasons behind the delays, the real problems have appeared to come, as with the Jubilee Line extension, in the mechanical and engineering (M&E) and fit-out phase. There have been widespread reports of installed M&E work in stations and tunnels having to be ripped out and replaced because of incorrect or incomplete initial designs. In addition, M&E workers at one station 鈥 Woolwich 鈥 went on strike at the start of this year over bonus payments.

鈥淐ompensation events鈥

It does appear that initial civil engineering works on the project progressed well 鈥 with the NAO report making clear Crossrail managed to save 拢500m by procuring the work at the bottom of a recession. However, even here, costs mounted above predictions, with one source claiming contractors had made around 拢500m of additional claims (known as 鈥渃ompensation events鈥 in the NEC contracts being used) made against the project by 2016. Even by 2014, in fact, the detail of the NAO report makes clear that the real outturn cost of contracts was somewhat higher than the targeted contract price. 

The annual ministerial progress update in summer 2017 was the first government admission of 鈥渃ost pressures鈥 on the project, which by February this year Crossrail鈥檚 Morgan admitted was pushing the project 鈥渧ery close on the funding envelope鈥.

Construction unions see this all as a vindication of warnings they have been making for some time. Bernard McAulay, national officer for construction at Unite, says: 鈥淚t鈥檚 been a complete shambles, to put it mildly. They鈥檝e had people designing things, and then the designs change after they鈥檝e been put in and it has to be taken out. These problems have been all over the project. The organisation has been in denial mode.鈥 Nevertheless, a spokesperson for Crossrail denied that any such problems were behind the announced delay.

37064610261_e71bb38bcf_o

Work is ongoing at Crossrail

鈥楥learly failing鈥

Some allege that leadership changes, with the departure of Crossrail鈥檚 longstanding chief executive, Andrew Wolstenholme, in May this year, at the same time the project鈥檚 chair Morgan was also given the job of chairing HS2, have compounded the problem. Labour Party peer Lord Adonis has said transport secretary Chris Grayling should not have allowed this to happen on a 鈥減roject that was clearly failing鈥.

Meanwhile, those in charge are not able to give any real assurances on exactly when the project will now open, and how much it will cost. TfL commissioner Mike Brown was due to meet with Treasury officials last Thursday to start the process of determining final costs, telling the London Assembly: 鈥淚t鈥檚 early days in the assessment of the cost over and above [what is] agreed. We don鈥檛 have certainty as to what those costs may be yet as it鈥檚 very programme dependent.鈥 

It is also clear that a detailed programme of the remaining works, which include, according to Wright, 鈥渟everal months鈥 of full-time testing, then trial running without people, then trial operations involving people, before regulatory approval of the safety case, is still being worked up. Hence Crossrail is not able to give any estimate of the date for full opening of the line 鈥 meaning through running from Reading, Berkshire, in the west to Abbey Wood, south-east London, and Shenfield, Essex, in the east 鈥 which was due at the end of next year. London mayor Sadiq Khan said he was 鈥渆xtremely frustrated, disappointed and angry about the delay鈥, adding: 鈥淲e鈥檙e awaiting a revised schedule; from that will flow an estimate of the cost.鈥

Reputation

As more details emerge, it will be possible to gauge the impact of the troubles on the reputation of UK construction, which many saw as having recovered with the successful delivery of the Olympics, only to be hit this year by the collapse of Carillion and delays to Tottenham Hotspur Football Club鈥檚 new ground. Former Conservative transport minister and ex-TfL board member Steve Norris is sanguine. 鈥淭here have to be questions about the late notification of these problems. But overall this has been well-delivered, and the cost overrun is within what I think most people would say is a very reasonable envelope. 

鈥淚n the context of this incredibly challenging project I can鈥檛 say this will damage the construction industry.鈥

Others, however, are less optimistic. The senior contractor source says: 鈥淚t鈥檚 not yet a disaster for the industry]. But if we see another nine-month delay down the road then it will be a real disaster.鈥 Holden agrees: 鈥淚 think it sets us back quite a long way. Crossrail was perceived to be a successful project. This is not just a six-week delay 鈥 something pretty serious has to have happened to have this kind of delay.鈥 There is clearly a long way to go on this project 鈥 and, for the industry, a lot remains at stake.

Crossrail Timeline

2007鈥 Government agrees 拢15.9bn funding package for Crossrail

2009鈥 After royal assent to the Crossrail Act the year previously, work starts on the project at Canary Wharf railway station

2010 鈥 The project is reviewed and the budget is cut to 拢14.8bn to offset already rising costs as austerity measures are introduced by the coalition government 

2011鈥 Rob Holden steps down as chief executive. Procurement of rolling stock reviewed. Andrew Wolstenholme appointed new chief executive

2012鈥 Crossrail tunnelling starts

2014鈥 Rolling stock contract awarded to Bombardier. National Audit Office says project is managing public money well, but notes it is slightly behind on schedule and cost

2015鈥 Major tunnelling and engineering work completes, fit-out phase begins

2016鈥 First reports emerge of M&E work being installed then ripped out, then re-installed. Unite later brands Crossrail 鈥渢he Hokey Cokey line鈥

June 2017鈥 Transport minister Paul Maynard admits 鈥渃ost pressures鈥 but says government is working with TfL to 鈥渆nsure that the project is being effectively managed and will be delivered within funding and on schedule鈥

November 2017鈥 Explosion at a substation at Pudding Mill Lane station as two voltage transformers fail, delaying track operation until February

December 2017鈥 Unite announces M&E staff at Woolwich to go on strike in pay dispute

February 2018鈥 Crossrail chair Terry Morgan admits project 鈥渧ery close on the funding envelope鈥

March 2018鈥 Crossrail announces Wolstenholme to leave in May

May 2018鈥 First reports that project has gone over budget. Crossrail officially informs London mayor Sadiq Khan on 31 May of cost increases

June 2018 鈥 Crossrail board first informed by executive of rising pressure on the programme due to signalling testing not progressing as hoped

July 2018鈥 Transport minister Jo Johnson announces 拢590m increase in Crossrail budget, to 拢15.4bn. Crossrail board told programme situation 鈥渘ow very difficult鈥, with a special board meeting convened in August. TfL commissions independent review of programme

August 2018鈥 Special board meeting on 29 August decides it is no longer possible to safely and reliably open central section in December. Public announcement 31 August

September 2018鈥 Work commences to re-programme works and cost the new schedule