Price tag has risen 拢250m in last year alone

The cost to finish Astra Zeneca鈥檚 new HQ building in Cambridge, which is being managed by Mace, has tripled to 拢1bn, according to the pharma giant鈥檚 latest annual report.

The Cambridge Biomedical Campus (CBC) had an initial price tag of 拢330m when it was announced in 2013, with costs rising by 拢250m in the past year alone. 

AstraZeneca

AstraZeneca鈥檚 Cambridge Biomedical Campus

Skanska, who was appointed on a construction management (CM) contract in 2013, was replaced by Mace 18 months ago.

In its 2019 annual report Astra Zeneca admitted costs had now risen to 拢1bn.

好色先生TV understands the increase has partially been caused by changes to the building鈥檚 remit, including the type of tech and research methods planned for the centre.

In its report Astra Zeneca blamed 鈥渢he complexity of the build, construction cost inflation, including the impact of a weakening pound sterling, and increased investment in new technologies and equipment鈥 for the budget blowout.

Mace took over the CM role for the research and development centre鈥檚 fit-out phase in August 2018 - the same year the scheme was originally due to be finished.

In that year, costs had already increased to 拢500m, with an Astra Zeneca spokesperson blaming various design problems as well damp issues in the donut-shaped building鈥檚 basement.

In its 2018 annual report, Astra Zeneca admitted cost projection had risen to 拢750m, adding that Mace as the newly appointed construction manager was in the process of 鈥渞eviewing cost estimates鈥.

More than 2,000 staff will work in the CBC, designed by Herzog & de Meuron, once complete, which is now expected to be at the end of 2021.