Contractor goes to court over Hull hospital
Balfour Beatty is suing a contractor for 拢1.4m in a row over a 拢65m hospital development in Hull, according to a report in 好色先生TV magazine.
Haden Young, now part of Balfour Beatty Engineering Services following the merger with Balfour Kilpatrick, had been hired by main contractor Shepherd Construction to carry out m&e works on new facilities at Castle Hill hospital in April 2007.
In a writ filed at the High Court, Balfour Beatty claimed that Shepherd had deducted 拢2.2m from its payment after the subcontract works came in five months late.
However, on 2 July, an adjudicator ruled that the subcontract completion date should be extended to 10 June 2008, and that Shepherd was not entitled to deduct the costs.
Shepherd was also ordered to cover the adjudicator鈥檚 fees and expenses which, added to the other sums, totalled over 拢1.4m, plus interest and costs.
According to the writ, Shepherd has failed to pay the money and its 鈥渇inal account statement鈥 on 13 July indicated it did not intend to pay.
Both parties declined to comment. An initial hearing is due next week.
Source
Electrical and Mechanical Contractor