Keep up to dateTable 1: Indicative costs of land remediation techniques* | ||
Remediation technique | Unit | Rate (£/unit) |
Removal | disposed material (m3) | 40-140 |
Clean cover | surface area of site (m2) | 20-40 |
On-site encapsulation | encapsulated material (m3) | 20-75 |
Bio-remediation | treated material (tonne) | 30-80 |
Soil washing | treated material (tonne) | 40-80 |
Soil flushing | treated material (tonne) | 60-100 |
Vacuum extraction | treated material (tonne) | 50-100 |
Thermal treatment | treated material (tonne) | 750-1200 |
* excluding landfill tax |
Table 2: Variation in the costs of land remediation by removal* | |||
Disposal Volume (less than 3000 m3) (£ /m3) | Disposal Volume (3000-10 000 m3) (£ /m3) | Disposal Volume (more than 10 000 m3) (£ /m3) | |
General items and site organisation costs | 40-60 | 20-35 | 5-15Ìý |
Site investigation and testing | 3-10 | 2-5 | 1-3 |
Excavation and backfill | 12-20 | 9-18 | 6-12 |
Disposal costs* | 15-30 | 20-35 | 25-45 |
Haulage | 10-20 | 9-12 | 8-15 |
Total ( £/³¾3) | 80-140 | 60-105 | 45-90 |
Allowance for site abnormals | 0-5+ | 0-15+ | 0-10+ |
* Disposal costs include tipping charges but not landfill tax | |||
Table 3: Typical 1999 tipping charges* | |
Waste classification | Charges (£/tonne) |
Non-hazardous waste | 5-10 |
Hazardous waste | 10-20 |
Special waste | 12-25 |
Contaminated liquid | 12-35 |
Contaminated sludge | 35-45 |
* Excluding of landfill tax |
Cost model | |||
element cost | £/³¾2 disposal material | of total cost | |
General items | 137 300 | 22.33 | 22.65% |
Performance bond and insurance | |||
Site accommodation | item @ £4000  | ||
Fixed charge | item @ £6000 | ||
Time related charge | 10 weeks | @ £950 | |
Traffic management; traffic management measures, wheel wash facilities and weighbridge | |||
Fixed charge | item @ £4000 | ||
Time related charge | 10 weeks | @ £550 | |
Health and safety; protective equipment; provisions for CDM; boundary fences | |||
Fixed charge | item @ £2000 | ||
Time related charge | 10 weeks | @ £250 | |
Plant mobilisation and set up | |||
Fixed charge | item @ £2800 | ||
Time related charge | 10 weeks | @ £4000 | |
Site administration | 10 weeks | @ £4000 | |
Site security, out of working hours | 10 weeks | @ £600 | |
Temporary works | item @ £15 000 | ||
Site investigation | 19 000 | 3.09 | 3.13% |
Trial pits and boreholes | item @ £3500 | ||
Allowance for laboratory analysis | item @ £15 500 | ||
Excavation | 14 550 | 2.37 | 2.41% |
Site clearance, generally | 5000 m2 | @ £0.10 | |
Excavation, generally | 6000 m3 | @ £0.75 | |
Breaking out hard artificial materials; tarmac exposed at commencement surface | 150 m3 | @ £3.00 | |
Breaking out hard artificial materials; brickwork exposed at commencement surface | 150 m3 | @ £4.50 | |
Breaking out hard artificial materials; mass concrete exposed at commencement surface | 150 m3 | @ £5.00 | |
Breaking out hard artificial materials; reinforced concrete exposed at commencement surface | 150 m3 | @ £8.50 | |
Breaking out hard artificial materials; brickwork not exposed at commencement surface | 100 m3 | @ £5.00 | |
Breaking out hard artificial materials; mass concrete not exposed at commencement surface | 150 m3 | @ £6.00 | |
Breaking out hard artificial materials; reinforced concrete not exposed at commencement surface | 250 m3 | @ £11.00 | |
Trimming excavated surfaces | 5000 m2 | @ £0.20 | |
Preparation of excavated surfaces | 5000 m2 | @ £0.25 | |
Disposal | 230 800 | 37.53 | 38.07% |
Disposal of non-hazardous waste material; direct from excavation; excluding haulage costs | 6300 t | @ £7.50 | |
Disposal of hazardous waste material (Class U2); direct from excavation; excluding haulage costs | 2400 t | @ £12.00 | |
Disposal of hazardous waste material (Class U3); direct from excavation; excluding haulage costs | 3600 t | @ £15.00 | |
Disposal costs; allowance for tip charges related to special waste regulations | 200 loads | @ £15.00 | |
Disposal costs; haulage, based on 125 mile round trip | 85 000 miles | @ £1.15 | |
Filling | 142 020 | 23.09 | 23.42% |
Material arising from the site screening and crushing process | 950 m3 | @ £1.50 | |
Imported material; excluding haulage costs | 12 300 t | @ £7.00 | |
Extra for double handling of excavated materials on-site, associated with crushing and screening | 1 900 m3 | @ £1.05 | |
Extra for haulage costs of imported fill; based on 50 mile round trip | 35 000 miles | @ £1.50 | |
Screening | 2850 | 0.46 | 0.47% |
Screening; generally | 950 m3 | @ £3.00 | |
Crushing | 4750 | 0.77 | 0.78% |
Crushing; generally | 950 m3 | @ £5.00 | |
Contingencies | 55 000 | 8.94 | 9.07% |
Contingency sumAllow 10% | item @ £55 000 | ||
Total construction cost | 606 270 | 98.58 | 100% |
Extra costs and savings | ||
Net extra £/³¾3 of disposed material* | ||
General items | ||
Extra for extra week in programme duration | 1 week @ £10 000 | 1.79 |
Excavation | ||
Extra for depth of excavation in excess of 5 m below commencement level | 1000 m3 @ £1.50 | 0.27 |
Extra for 100% increase in volume of hard artificial material (average rate used) | 1100 m3 @ £6.60 | 1.3 |
Disposal | ||
Deduction for reduction in tipping charges, based on a 10% decrease (average rate shown) | 12 300 t @ £9.50 | – 2.33 |
Extra for increase in tipping charges, based on a 25% increase (average rate shown) | 12 300 t @ £13.20 | 5.82 |
Change in proportions of waste to: non-hazardous waste (75%), hazardous (15%), special (10%) (average rate used, special waste charges excluded) | 12 300 t @ £8.95 | –3.63 |
Change in proportions of waste to: non-hazardous waste (40%), hazardous (30%), special (30%) (average rate used, special waste charges excluded) | 12 300 t '@ £11.10 | 1.16 |
Change in proportions of waste to: non-hazardous waste (30%), hazardous (20%), special (50%) (average rate used, special waste charges excluded) | 12 300 t @ £12.15 | 3.47 |
Deduction for 10% reduction in haulage rate; based on round trip of 125 miles | 85 000 miles @ £1.04 | –1.12 |
Extra for 25% increase in haulage mileage; based on round trip of 125 miles | 85 000 miles @ £1.44 | 2.96 |
Reduction for decrease in haulage mileage; based on round trip of 50 miles | 34 000 miles @ £1.15 | –10.49 |
Extra for increase in haulage mileage; based on round trip of 150 miles | 103 000 miles @ £1.15 3.70 | |
Filling | ||
Deduction for 5% reduction in imported fill costs | 12 300 t @ £6.65 | –0.52 |
for 10% increase in imported fill costs for reinstatement; imported top soil, | 12 300 t @ £7.70 | 1.04 |
300 mm thick; in lieu of imported fill | 5 000 m2 @ £5.50 | 1.16 |
Reduction in overall cost for increased volume of fill material recovered from site screening and crushing, based on 100% increase of volume to 2200 m3 (rate allows for double handling, screening, crushing and placing) | 1100 m2 @ £10.55 | 0.94 |
* Negative numbers are savings; costs are inclusive of contingencies | ||