- ºÃÉ«ÏÈÉúTV
All the latest updates on building safety reformRegulations latest
- Focus
- Comment
- Programmes
- CPD
- ºÃÉ«ÏÈÉúTV the Future
- Data
2024 events calendar
ºÃÉ«ÏÈÉúTV Awards
Keep up to date
- ºÃÉ«ÏÈÉúTV Boardroom
All the latest updates on building safety reform
2024 events calendar
ºÃÉ«ÏÈÉúTV Awards
Keep up to dateElemental cost analysis | ||||
Element | Total cost | £/³¾ | % of total cost | Specification |
Substructure | 1,193,996 | 55.86 | 3.10 | CFA piles, groundbeams and groundbearing slab |
Superstructure | ||||
Frame | 1,616,699 | 75.63 | 4.20 | Steel frame, 9 x 9 m grid; intumescent paint fire protection |
Upper floors | 555,000 | 25.96 | 1.44 | Composite deck |
Roof | 1,579,070 | 73.87 | 4.10 | Kalzip standing sseam zincwith Northlights and curved ridges |
Stairs | 671,389 | 31.41 | 1.74 | Internal feature stairs and fire escape pcc stairs |
External walls | 3,232,036 | 151.20 | 8.39 | Brickwork, lightweight steel inner leaf, zinc feature cladding |
Windows and doors | 1,852,078 | 86.65 | 4.81 | Aluminium cladding and frame system with security and acoustic rated glazing |
Internal walls and partitions | 1,312,509 | 61.40 | 3.41 | Highly cellularised part glazed space with full height doors |
Internal doors | 418,948 | 19.60 | 1.09 | Full height doorsets |
Internal finishes (to Category B occupant’s fit out) | ||||
Walls | 584,942 | 27.37 | 1.52 | Ceramic tiling and painted walls; plaster to walls |
Floors | 1,484,399 | 69.44 | 3.85 | Raised floor and carpet tiles; screed to atrium base; feature timber and stone; flooring to central areas |
Ceilings | 1,181,042 | 55.25 | 3.07 | Glass-reinforced-gypsum suspended ceiling tile system and atrium soffit (acoustic rated) |
Fittings and furnishings | 1,922,809 | 89.95 | 4.99 | WC cubicles, blinds, signage, shopfronts, glazed screens, specialist joinery, kitchen equipment |
Services | ||||
Mechanical installations | 6,101,923 | 285.46 | 15.84 | Central roof plantroom, four-pipe fire control units, 6x6 m |
Electrical installations | 3,393,995 | 158.78 | 8.81 | Market model upgraded for highly cellularised space |
Lift installation | 223,700 | 10.47 | 0.58 | Four lifts overall |
Fire protection | 265,770 | 12.43 | 0.69 | Drop-down smoke curtains, fire alarm systems |
Communication installations | 631,497 | 29.54 | 1.64 | Data cabling only (equipment by client) |
BWIC | 245,916 | 11.50 | 0.64 | |
Main contractor costs | ||||
Preliminaries, profit and overheads | 3,935,889 | 184.13 | 10.21 | |
Sub-total | 32,403,609 | 1,515.93 | 84.10 | |
External works/infrastructure | 6,128,467 | 286.71 | 15.90 | Brownfield site requiring utilities, groundwater control, amenity landscaping and high ratio car parking |
Total construction cost | 38,532,076 | 1,802.63 | 100.00 | |
Guillemont Park (Phase 1) Completion date: September 2000 Gross internal floor area: 21,289m2 over two similar three-storey office buildings with rooftop plantrooms |
Site powered by